Construction according to Party A’s requirements! The collapse of high formwork caused 6 deaths and 4 injuries! Three people were sentenced

As the saying goes, heaven has good reincarnation.

The supervision unit does not perform its duties conscientiously, and the on-site supervision is in vain.

Many designers have had the experience of being forced by Party A to produce electronic layout or white layout.

However, if the following case is shown to Party A, it is estimated that they will converge a lot.

The judgment documents show that: 1.

12 commercial building and is not connected with the building structure of No.

254), his behavior is suspected of a crime and has been handed over to the judicial authority for handling; He was criminally detained on November 15, 2016 and arrested on December 22, 2016.
.

(1) There is no legal and effective construction drawing design document for the construction of the gate decoration framework, and the Project Supervision Department has not put forward rectification suggestions to the construction unit; (2) It is found that the project manager of the construction unit has not been on duty for a long time, the project department has no full-time safety production administrator, the high formwork construction has not prepared a special construction plan and has not organized experts to demonstrate and other major safety hazards, has not issued a written rectification notice or shutdown order, and has not timely reported to the relevant competent department about the construction unit’s refusal to rectify.

3、 The defendant Dai Huax (the special supervision engineer of Hongyun Jiangshan International Project) committed the crime of major responsibility accident and was sentenced to two years and six months’ imprisonment and three years’ probation.

The main responsibility of the construction unit for safety production is not implemented, and the site management is chaotic.

The main responsibility of the construction unit for safety production is not implemented, and the project is neglected in management.

3 commercial building.

(1) The company has not established and improved the safety production responsibility system and safety production rules and regulations; (2) There is no legal and valid construction drawing design document for the construction of the gate decoration framework, and only the electronic layout provided by the design institute through the electronic mailbox, which illegally requires the construction unit to construct; (3) Lack of unified coordination and management of the safety production work of the construction company, especially for the safety hidden dangers such as the construction company’s Hongyun Jiangshan International Project Manager who has not been on duty for a long time, the filing full-time safety officer who has not been on duty in the project department, and the high formwork construction without special construction plan, and failure to urge the rectification in time.

Magnetic Recess Former

254), etc., and the structure is incomplete: the vertical and horizontal distance of the upright pole of the support frame is 800-1000mm × 800-1000mm, with a step distance of about 1500-1700mm, the beam bottom support system has not been densified, and the top of the steel pipe vertical pole supporting the beam plate has not been supported with adjustable bracing; The vertical and horizontal horizontal tie rods are not fully set at each step; The horizontal and longitudinal cross bracing are not set in the frame as required, and the number of transverse cross bracing is not enough and is not set continuously from bottom to top; The ratio of height to width of the formwork support system (about 16:7.3) is more than two times.

3.

The defendant Zhu x (deputy general manager of the construction unit) committed the crime of major responsibility accident and was sentenced to two years’ imprisonment and two years’ probation for six months.

2、 The defendant Kuang xx (deputy manager of Hongyun Jiangshan International Project of the construction unit) was sentenced to two years’ imprisonment and two years and six months’ probation for the crime of major liability accident.

34 persons were dealt with (1) The personnel proposed to be handed over to the judicial authority for treatment 1.

The structural measures to ensure the stability of the frame are seriously insufficient.

2.

Accident review Direct cause The high formwork erection of the accident belongs to the divisional and subdivisional works with greater risk than a certain scale.

Three people were sentenced! Recently, it was learned from the China Judicial Documents Network that the People’s Court of Langzhong City recently made a first instance judgment on the case.

(1) The project manager of Hongyun Jiangshan International has been absent for a long time, and the deputy manager of the project department and other management personnel and the safety production management organization have not fulfilled their safety production management responsibilities; (2) Failing to carry out safety production education and training for employees in accordance with national regulations, especially failing to carry out “three-level” safety production education and training for new employees; (3) For high-risk high-formwork projects, the special construction scheme was not prepared according to the national regulations, and experts were not organized to demonstrate the special construction scheme; (4) Organize the operators who have not obtained the qualification certificate for special operation of construction scaffold to set up high formwork; Failing to carry out safety technical disclosure to site management personnel and operators before erection; Failure to organize acceptance as required after erection; (5) Before concrete pouring, it is not confirmed by the technical director and director of the project whether the safety production conditions for concrete pouring are met; There is no full-time safety officer to supervise the pouring process.

Photos of the accident site ↓ Indirect cause 1.

Its erection does not comply with the provisions of the Technical Code for Safety of Building Construction Formwork (JGJ162-2008), the Guidelines for Construction Safety Supervision and Management of High Formwork Support System in Construction Projects (JZ [2009] No.

Who has the heaven spared? Case judgment and investigation report During the construction of the decorative framework of the door of the commercial and residential building in Hongyun Jiangshan International Community, Langzhong City, Sichuan Province, the high formwork collapsed, resulting in 6 deaths and 4 injuries (including 2 serious injuries), with a direct economic loss of about 5 million yuan.

The support frame is only set with a connection point on the roof of No.

Zhu x, male, the deputy general manager of the construction unit, concurrently serving as the technical director, and concurrently serving as the project technical director of the construction unit, ordered the construction unit to construct according to the invalid electronic layout provided by the design institute; Failing to organize the preparation of special construction plans and provide false information to the accident investigation team in accordance with the provisions of Article 2.1.1 of the Guidelines for the Safety Supervision and Management of High-supported Formwork Construction of Construction Projects (JZ [2009] No.

Why do different parties have the same requirements? Because they believe that the drawings are designed by the design institute, and the construction is done by the construction unit, and the responsibility has nothing to do with Party A, but the extra huge benefits obtained from this are Party A.