Harbin Airport Economic Zone Grasps the Construction Period and Guarantees the Progress, Initiating a Construction Boom in Winter

In the face of severe cold weather, we still stick to the front line of construction, continue to launch the “winter offensive”, focus on production, promotion and safety, steadily promote winter construction, and lay a solid foundation for the construction task to seize the opportunity later this year.

Round Bar Ferrule

Source.

For more highlights, please click the blue text above to follow us! During the construction of the bridge project of the Airport Third Avenue, the freezing temperature of minus 20 degrees could not resist the enthusiasm of the developers and builders of the Airport Economic Zone.

It is understood that a bridge with a length of 100 meters, four spans and each span of 25 meters, is set up across the rainwater drainage channel on the 3rd Airport Avenue.

The upper part of the whole bridge consists of 40 prefabricated small box girders, and the lower part consists of 30 bored piles, 18 pier columns, 4 abutments, and 6 capping beams.

The completion and opening of the project will further improve the internal and external road network in the airport economic zone, provide transportation support for enterprises in the airport economic zone, and promote the healthy development of industrial projects in the airport economic zone.

The lower part of the bridge has been completed by the end of September.

The lifting of the upper small box girder is under way, and it is planned to be completed and opened to traffic at the same time as the road project by the end of August 2023.