Name of Party B’s representative on the site: Title: If you need to change the person, you need to notify the other party seven days in advance.
4.
Provide the progress of the project to Party A’s representative, and timely report to Party A’s representative and relevant departments in case of any project accident.
Construction organization 1.
If Party B fails to start work on time, it shall put forward the reasons and requirements for delaying the commencement to Party A in writing.
In the process of construction, if the technical requirements and the actual situation of the site are found to be inconsistent with the National Code for Fire Control Acceptance, it shall be proposed to Party A, which shall be solved by Party A and the design unit through consultation with the fire department.
5.
Site representative 1.
on the construction site of Party B.
If there is no force majeure, Party B shall complete the project within the time specified in the contract.
The construction shall be carried out according to the design drawings approved by the fire department and the Code for Fire Protection Design of Buildings and other relevant provisions.
Name of Party A’s representative on the site: Title 2.
Contract price: the total project price is RMB (in words)________________ Yuan (¥ yuan), all taxes payable for the project are___ Party A.
Commencement and delayed commencement Party B shall start construction according to the commencement time agreed in the contract.
6.
3.
In case of any damage during the period, Party A shall be promptly assisted to repair it.
Click on the blue letter to pay attention to us in case of emergency~Fire engineering construction contract project name:_______________________________________________ Construction unit:_______________________________________________ Construction unit:_______________________________________________ Contract of fire engineering project on MM/DD/YY Construction unit:_______________________________________________ (hereinafter referred to as Party A) Construction unit:_______________________________________________ (hereinafter referred to as Party B), in accordance with the relevant provisions of the Contract Law of the People’s Republic of China and the Regulations on Construction and Installation Project Contract, in combination with the relevant provisions of Shanxi Province and the specific situation of the project, through friendly negotiation, both parties have reached the following terms: 1.
5.
Party A shall provide three copies of construction drawings to Party B seven days before the commencement of construction.
Provide construction site with construction conditions.
Due to Party A’s reason, the construction cannot be started according to the commencement time agreed in the contract.
After the completion of the project, Party B shall assist Party A to handle the fire control acceptance procedures.
2.
Party A shall notify Party B in writing to postpone the commencement time and the construction period shall be postponed accordingly.
.
Protect the equipment, wiring, pipelines, etc.
3.
Other work agreed by Party A to be done by Party B: IX.
In case of any change during the construction, it shall timely coordinate with Party B and the design unit to solve the problem and provide the water, electricity and telecommunication lines required for the construction and connect them to the construction site.
The representative of Party A shall reply to Party B in writing within 48 hours after receiving the application for delayed commencement.
7.
Contracting method: labor and materials.
Assist Party A in the protection of the finished products of the completed project.
4.
Party B agreed that Party A should do other work: VIII.
Project contract price and contracting form: 1.
If the project needs to be reserved and embedded by the infrastructure construction party, Party A shall negotiate with Party B and the infrastructure construction unit in advance.
Party A shall provide the design data approved by the local fire department.
Project overview: project name:____________________________________________________ Project location:_____________________________________________________ Project scale:_____________________________________________________ Investment approval number:_________________________________________________ Project content:_____________________________________________________ Contracting scope:_____________________________________________________ 2、 Date of commencement of construction period: Date of completion: Date of completion of the project and related product quality The equipment and project quality required by the project provided by Party B meet the fire control acceptance standards.
If the construction period and acceptance delay are affected by the relevant equipment provided by Party B, Party B shall be fully responsible for the losses caused to Party A.
Party B’s work 1.
The cost of product quality problems shall be borne by Party B, and other damages caused by human factors shall be borne by Party A.
2.
During the construction process, due to the failure to pass the fire control construction application and related procedures, the work to be installed by Party B shall be the responsibility of Party B, and other engineering reasons shall be coordinated by Party B with Party A.