Site Construction of Rongchuang Project

Today, there are 52 constructors in A36 plot, including 26 masons, 1 water and electricity worker, 2 scaffolders, 5 plasterers, 2 carpenters, 7 rebars, 3 elevators and 6 tower cranes.

As the general contractor closed the account at the end of the year for Plot A31, the payment for concrete and reinforcement materials could not be paid, and the concrete could not be supplied, which led to no construction on site.

4.

3.

Due to the closing of accounts by the General Contractor at the end of the year for Plot A22, the payment for concrete and reinforcement materials could not be paid, and the concrete could not be supplied, resulting in no construction on site.

6.

(The Seventh Engineering Bureau will coordinate with the concrete mixing plant and the reinforcement manufacturer before this Thursday, strive to recover the material supply after payment, and coordinate with the labor team to complete the roof capping of Building 5 # and the closed concrete pouring of the basement roof structure.) 5.

Plot B04: Today, there are 115 people working on the site, including 29 general contractors, 20 thermal insulation workers, 8 garden workers, 9 hardbound workers, 2 curtain walls, 5 external walls, 7 doors and windows, 12 fire protection workers, 10 elevator operators, 4 gas operators, 2 intelligent workers, 2 three networks workers, and 5 Baiye workers.

1.4 Site construction of Rongchuang Project 1.

The slabs to be poured for each building will be poured.).

The total number of constructors in Plot 1617 is 105, including 4 for indoor paint construction, 7 for construction elevators, 8 for thin plastering, 12 for water and electricity teams, 21 for thermal insulation construction, 10 for fire protection, 4 for door and window installation, 3 for railings, 6 for tap water, 26 for facades, and 4 for commercial entities.

The total number of people in the field construction of Plot A20 today is 47: 3 for masonry, 8 for plastering, 5 for aluminum formwork, 5 for wood formwork, 12 for handyman, and 6 for tower cranes, There are 8 people in the elevator (many workers of the project are infected with symptoms, and they will return to work after recovery).

B04A1617A20A36。.

Fixing Socket Cross Pin Nail Plate

(The Seventh Engineering Bureau will coordinate with the concrete mixing station and the reinforcement manufacturer before this Thursday, and strive to recover the material supply after payment.

2.