The construction will not be closed during the Spring Festival and the construction period will be guaranteed

According to the reporter, in the past three years, Harbor Construction Group has accumulated 86 QC achievements, 11 provincial and ministerial construction methods, and 58 national patents.

“Many colleagues in the project department are from other places.

At 8 a.m., Jiao Wei and his colleagues sat in the conference room of the Project Department for the morning meeting on time, and 13 staff members sat around to arrange and deploy the construction arrangement of the day, discuss the construction plan, and study whether there is room for optimization.

At seven o’clock in the evening, Jiao Wei, who had just returned home, received another call from the construction unit.

In the face of such difficulties, the Project Department has continuously optimized the construction plan and set up a ship dispatching room for ship control.

On the second day of the Spring Festival, the construction site of the port project is still a busy scene when the whole country is reunited.

In the face of complex wharf works, the Project Department shall make scientific deployment and reasonable allocation, and take the dredging of harbor basin and berth as an important part of the construction during the Spring Festival to ensure the comprehensive progress of the construction operation.

He put down his backpack, did not rest, opened his laptop, and then continued to make the report document.

How to allocate each ship properly is the key to give full play to the maximum efficiency of the construction ships, shorten the project duration, reduce costs and increase efficiency, so that it can not only not conflict with the production and operation of the wharf, but also coordinate the mobilization order of the construction ships according to the different progress, so that the construction can be closely connected.

Lifting Anchor

When turning, he sees several crawler cranes standing beside the gantry crane, which is the construction site of berths # 18 and # 20.

Jiao Wei kept writing and drawing with a ballpoint pen in his hand, and recorded the mentioned optimization scheme in his notebook.

Looking at the caissons looming in the sea, it seems that the future magnificent wharf has appeared in front of us.

The project keeps going.

Due to the intersection between the construction area of the project and the production and operation area of the wharf, the construction ships can reach more than 30 after the various offshore processes are fully carried out.

A cold air during the Spring Festival brought the temperature of sunshine to minus 7 degrees.

“At 6:30, Sheng Songgong 899 docked at the Japanese port barge for 10 ships.

We have taken a comprehensive consideration and adopted the rotation system.

The thick notebook recorded the details of the project, and also witnessed the rise of new docks.

At 8:00, the town navigation engineer 518 positioned…” Chen Qinglin, the production director, is accurate the ship use plan to every minute according to the site situation.

His wife urged him to eat.

Jiao Wei, the project director of general berths # 18 and # 20 in the south of Lanshan Port Area of Rizhao Port, is driving along the West 10th Road to the east.

After the morning meeting, the colleagues of the project department rushed to the construction site and started the day’s work in the cold wind.

It has won the “reform and innovation demonstration enterprise” in the labor competition for tackling the key work of the provincial housing construction system.

At the construction site of # 18 and # 20 general berths in the southern operation area of Lanshan Port Area of Rizhao Port, undertaken by Rizhao Branch of Shandong Port Construction Group, the construction was not closed during the Spring Festival, and the builders still worked overtime and worked hard at the front line of the project, and made every effort to seize the schedule and guarantee the construction period with a hot construction offensive to fight for the “opening of the Year of the Rabbit”.

However, the construction period of berth # 20 and the rear yard is still tight and the task is heavy.

Many projects have won the honorary titles of Zhan Tianyou Award of China Civil Engineering, the National Quality Engineering Award, the “Taishan Cup”, and the “Shandong Province Construction Engineering Quality Structure” More and more fields such as construction have changed from “runner” to “fellow runner” or even “leader”.

In the early morning, the traffic on the roads in the port area was sparse, and the lanterns on the roadside lamps were bright in color, embellished with a cheerful flavor in the cold wind.

In order to ensure the node construction period and ensure the smooth construction after the festival, the project department resolutely decided not to take a holiday during the Spring Festival, and made every effort to seize the time and ensure the progress.

In fact, this is not a big problem for their project department.

What really tackles the difficulties and shows the construction level is that they have constantly innovated the technology in the process of engineering construction, tackled the topics of “intelligent shipment of caissons”, “material corrosion prevention”, “concrete additives”, “vacuum preloading soft foundation treatment”, and led the industry’s technological innovation The second phase of the Rizhao Port International Trade Project has promoted the popularization of smart chemical sites on the basis of good results achieved in the pilot project of smart chemical sites.

Some of our colleagues from far away from home went home for the New Year ahead of time and returned to work ahead of time after the New Year.

As a key construction project of Shandong Port, the project department of # 18 and # 20 general berths in the south of Lanshan Port Area of Rizhao Port completed the main construction of # 18 berths five days in advance in 2022.

Reporter | Acting Xinxing Correspondent | Source of Feng Wenhao | Shandong Port.
.

Several of us, as local people in Rizhao, should keep up with and stay closer during the Spring Festival, so as to control the construction period and lay a solid foundation for the full production after the holiday.” An Zichao, the deputy project manager, checked the pipeline position of the yard behind the wharf while comparing the engineering drawings.

After the day’s construction, it is also necessary to sort out and summarize the project data.

He kept working and said in a hurry, “You eat first.” It was this hard work day after day that led to the rise of docks# Berth 18 has taken shape, and Berth # 20 is also in sight of victory.