Cut off construction, resume passenger transportation… Tangshan people, take a look! These messages are related to you!

▼▼▼ 01 Announcement of Broken Intersection – Old Tangfeng Road Announcement of Broken Intersection – Yuhua Road Rainwater Pipe Network (Jianshe Intersection – Old Tangfeng Road) The existing pipe trench can no longer meet the drainage requirements.

The construction period was from March 28, 2020 to June 20, 2020.

Recently, according to the demand for passenger flow in various regions and the relevant work requirements for epidemic prevention and control, the Transportation Group has resumed the operation of 10 intercountry passenger transport routes from the urban area to 7 counties and districts at its 15 bus stations
.

During the disconnection period, the vehicle detour plan is as follows: the left half of the bridge is under construction, and the up and down vehicles pass through the right half; The right half of the bridge is under construction, and vehicles traveling up and down will pass through the left half.

Vehicles passing by should pay attention to mutual courtesy and slow down.

Announcement on the Interruption of the Luanhe North Bridge on National Highway G205 Shanshen Line: The Luanhe North Bridge on National Highway G205 Shanshen Line (K122+549) in Tangshan City will undergo full width interruption construction, with a construction period from March 26, 2020 to June 20, 2020.

We apologize for any inconvenience caused by the construction.

We apologize for any inconvenience caused by the construction.

1, Shiliu River Bridge No.

Vehicles passing by please detour around the Luanhe South Bridge.

Cut off section and time: from March 30 to April 19, repair the expansion joint of Wangnianzhuang Middle Bridge of K22-K23 left section, and repair the expansion joint of left bridge of 205 National Highway to Tanggu Expressway.

Crown Foot Anchor

Now, the rainwater pipeline in this section is undergoing renovation and construction.

Tangshan Housing Construction Engineering Corporation Guye West Outer Ring learned from the Fourth Tangshan Traffic Police Brigade that due to the maintenance and construction of seven bridges, including the Wangnianzhuang Middle Bridge, Shiliu River Bridge No.

Reminder from the Fourth Traffic Police Brigade: During construction, roads are prone to congestion.

From April 20 to April 30, repair the expansion joint of the right bridge from 205 National Highway to Tanggu Expressway.

We apologize for any inconvenience caused by the construction.

The construction is scheduled to be completely cut off from April 2, 2020 to June 20, 2020.

Vehicles passing by please detour the Yafeng Line and Yuxin Line.

Tangshan Highway Maintenance and Management Center March 27, 2020 02 Tangshan 10 passenger transport routes have resumed operation in an orderly manner.

2, and Qiluan Railway Flyover, the construction of expansion joint in Guye West Outer Ring is planned to be broken in two sections from March 30 to April 30.

On March 27, 2020, the Tangshan Highway Maintenance and Management Center announced that the National Highway G509 Wologu Bridge was under full section disconnection construction.