According to the requirements, the city will build and renovate a batch of centralized isolation rooms based on the existing stock of 24223 isolation rooms.
Source | Hebei Daily Client
.
Baoding COVID-19 Shelter Hospital is located to the south of Fuxing West Road and the west of West Second Ring Road in the urban area.
In addition, wireless network coverage is also achieved, with the establishment of medical information systems, video surveillance halls, consultation halls, and remote consultation systems.
Among them, 9 large health stations with a capacity of over 1000 rooms will be built in the main urban area, Baobei, Baonan, and western mountainous areas.
In recent days, Baoding City has been integrating resources, seizing progress, accelerating the construction of shelter hospitals, health stations, and the renovation of centralized isolation sites, comprehensively improving isolation and treatment capabilities and levels, and striving to contain the spread of the epidemic in the shortest possible time.
At present, medical equipment is gradually being transported to the site, ensuring emergency use at any time, which can meet the isolation, observation, and treatment of mild and asymptomatic infections.
All large health stations will be completed by April 30th, and other isolation sites will also be gradually built and put into use.
Hundreds of workers are working day and night on the construction site.
The bed units implement Internet of Things management, and each nursing unit has an independent rescue room, rescue equipment, and medical intercom monitoring system.
It is reported that the hospital has a construction area of approximately 22000 square meters, with 2000 beds constructed.
At that time, the capacity of quarantine facilities in the city will reach 40723.
At the same time, Baoding City has also accelerated the construction of isolation sites in accordance with the principle of building a new batch, renovating a batch, and requisitioning a batch, to ensure that reception capacity can be quickly formed when the epidemic occurs.
More than 50% of the stations will be completed and put into use by April 15th.