The layout should be compact and reasonable, and the construction land should be minimized as much as possible.
2、 Layout content ▲▲▲▲ 1.
14.
When bulk materials are transported by railway, the first step is to solve the problem of railway introduction; When a large amount of materials are transported by water, the first consideration should be given to the use of the original dock and whether to add a dedicated dock; When a large amount of materials are transported to the construction site by road, due to the flexible arrangement of car routes, it is generally necessary to first arrange on-site warehouses and processing plants, and then arrange the introduction of off-site transportation
.
The construction layout should be strictly controlled within the building property line.
Construction transportation roads.
Production and living facilities for construction (processing shed, operation shed, warehouse, material yard, administrative management room, employee living room, etc.) 6.
9.
Fixing Socket Cross Hole Nail Plate
5.
11.
10.
The on-site arrangement is beneficial for the construction operations of each sub project.
13.
Consider the condition of the construction site and the traffic conditions of the main entrances and exits.
Comply with the hygiene and safety technical requirements of the construction site and fire prevention regulations.
7.
Implement strict safety and construction standards, and strive to create provincial-level safe and civilized construction sites.
4.
6.
Various construction machinery not only meet the needs of various working faces but also facilitate installation and disassembly.
Meet the needs of various professional work teams at different stages for dormitories, office spaces, and material storage and processing sites.
Construction Software 261 1.
The layout of various construction facilities should meet the requirements of convenient construction, safety and fire prevention, environmental protection, and labor protection.
Layout Principles ▲▲▲ 1.
3、 Layout steps ▲▲▲▲ Introduction of off-site transportation (railway transportation, waterway transportation, road transportation) → Layout of warehouses and material yards → Layout of processing plants → Layout of internal transportation roads → Layout of temporary administrative and living facilities → Layout of temporary water and electricity pipelines and other power facilities 1.
Proposed buildings or structures, as well as important facilities around them.
5.
Reasonably organize transportation, ensure smooth on-site transportation roads, and minimize secondary handling.
Try to utilize existing buildings or structures as much as possible.
3.
12.
2.
Location of mechanical station and garage 7.
Combining the proposed construction plan and sequence.
2.
In plane transportation, it is necessary to try to avoid mutual interference between civil engineering, installation, and other professional construction.
Meet the needs of semi-finished products, raw materials, turnover materials stacking, and steel bar processing.
Location of water sources, power sources, transformers, temporary water supply and drainage pipelines, as well as power and power facilities.
4.
3.
Location of all safety and fire protection facilities.
When designing the overall construction site plan for off-site transportation, the first step should be to study bulk materials, finished products, semi-finished products The transportation method for equipment and other items entering the construction site should be considered.
8.
Fixed position of construction machinery and equipment.