Synchronous construction technology of distribution box with structure

▶ Comprehensive benefits: free of materials and labor costs such as embedded wooden box production, secondary piping and box installation, secondary slot filling, etc., and save installation cost.

Click the blue words above to pay attention to the secondary construction required by our traditional construction method of distribution box, which is not conducive to cost reduction and efficiency increase, and is easy to cause common quality problems such as hollowing and cracking around.

The thickness of the distribution box out of the wall shall be the same and the elevation of the box top shall be the same; Avoid common quality problems such as hollowing and cracking around the distribution box.

During the formwork installation, the reinforced positioning distribution box structure shall be embedded and formed at one time, and the inside of the box shall be reinforced with stereotyped tools to ensure that the box is upright and not deformed, so as to avoid hollowing and cracking caused by the secondary construction of the box.

The distribution box shall be embedded synchronously with the primary structure, and the box shall be processed in a centralized manner.

II.

The prefabrication of the box body adopts factory centralized processing, the inside of the box body is reinforced with stereotyped tools, and the outside of the box body is positioned with reinforcement.

I.

You’d better watch it..

The distribution box shall be installed synchronously with the secondary structure.

Magnet Recess Former

The box precast blocks shall be made in advance according to the drawings and installed synchronously during masonry construction.

Factory processed box precast blocks are adopted; 3.

▶ Process flow: copy the level and set the elevation → fix the distribution box → lay and bind the line pipe → spot weld and fix → check and recheck → concrete pouring and tamping ▶ Process key points 1 Optimize the electrical embedded construction drawing, and determine the location of embedded box, pipeline direction and material size list; 2.

During masonry construction, the box precast blocks shall be built in place at one time according to the brick layout drawing.

The synchronous construction method of distribution box with structure is adopted to avoid common quality problems such as hollowing and cracking, save labor and material costs caused by secondary construction, and improve quality and efficiency.

▶ Process flow box pipeline connection → box prefabrication block fabrication → elevation positioning → masonry team assembly → pipeline connection → inspection and review ▶ Process key points 1 Specify the installation position of distribution box in the brick layout drawing; 2.

▶ Comprehensive benefits: the thickness of the distribution box out of the wall is the same, and the elevation of the box top is the same; Avoid the common quality problems such as hollowing and cracking around and improve the quality; Save labor and material costs for box chiseling, installation and slot filling.