Beijing: stop and resume work safety management at the construction site this winter and next spring

Flexible leave shall be implemented at the construction site, and reasonable arrangements shall be made for compensatory leave, off peak and return to Beijing.

Check the smoothness of the fire passage, and clean the materials and equipment blocking and occupying the fire passage.

For those who really need to leave Beijing to return to their hometown, carry out organized ticket purchase or “point-to-point” transportation.

It is of great political and historical significance to be the “host” of the Winter Olympic Games and do a good job in the safety production work on the construction site this winter and next spring.

Temporary fire-fighting equipment shall be equipped.

(IV) self inspect the safety of equipment and facilities on the construction site.

Loaders, excavators and other construction machinery shall be powered off, locked and parked in a unified area, and shall not be parked around the foundation pit.

Building materials such as reinforcement, steel pipe and formwork shall be stored in a centralized manner without exceeding the height, and all kinds of construction machinery shall not hinder social traffic.

Fixing Socket Waved End

The relevant requirements are hereby notified as follows: I.

February and March this year will usher in the Chinese traditional festivals Spring Festival and Lantern Festival.

Qualified enterprises can organize chartered cars or special trains to “point-to-point” transport labor workers to leave Beijing, educate and guide their personnel to do a good job in personal protection along the way, strictly implement local epidemic prevention and control measures after arriving in the countryside, and adhere to less gathering, less eating, less walking and less gathering..

All exposed earthwork on the construction site shall be covered, and reinforcement measures shall be taken for the dust net to realize “green eyes” on the construction site.

It coincides with the grand holding of the Winter Olympic Games and the national “two sessions” and other major activities in our city.

Conduct a comprehensive investigation on the electrical equipment in the office area and living area, cut off the power supply of high-power electrical appliances such as electric water heater and air conditioner that are not used during shutdown, and it is strictly prohibited for left behind personnel to use high-power electrical equipment without permission.

The construction unit shall comprehensively clean up all kinds of construction waste and domestic waste at the entrance and exit of the construction site, operation area, living area and office area.

carry out self inspection on the safety status of the construction site before shutdown (I) self inspection on the implementation of the main responsibilities of the safety production of the participating units.

Before the shutdown of the construction site, the construction unit shall take the lead in construction, supervision, design The survey unit shall set up a pre shutdown safety inspection team at the construction site to inspect the implementation of safety production responsibilities of each unit, timely and fully pay the safe and civilized construction cost and project progress payment to the construction unit in accordance with the contract, and supervise the construction unit to pay the wages of migrant workers in full; The suspension and resumption date shall be determined according to the construction period quota and the service guarantee requirements of major activities in the city, and the construction unit shall not be forced to rush for work; It is necessary to urge the survey unit to regularly carry out stability monitoring of dangerous and large projects such as deep foundation pit during shutdown, and require the design unit to issue design instructions on the safety guarantee measures that should be taken for the suspension of divisional and subdivisional works involving new structures, new materials, new processes and special structures.

The construction enclosure facade and external scaffold protection shall be clean and tidy, the edge and opening protection shall be firm, the tower crane boom, construction elevator car and construction basket shall stop at a safe position and cut off the power supply, and the tower crane shall be provided with anti climbing measures.

The District Construction Committee shall conduct spot checks on the safety status of important areas and key projects before shutdown.

(VI) self check the implementation of “Three Guarantees in front of the door”.

In order to highlight the safety service guarantee of the construction sites during the “two festivals”, “two sessions” and the Winter Olympic Games, strengthen the safety management of suspension and resumption of work at the construction sites of the city, and ensure that all kinds of production safety accidents will not occur at the construction sites during the shutdown, The work safety and epidemic prevention and control on the construction site are stable and orderly after the festival.

At the same time, the general contractor shall report the date of suspension and resumption of work and the contact person on the construction site during the suspension period to the district housing and Urban Rural Development Commission for filing.

Fire safety training shall be carried out for the personnel left at the construction site during the shutdown period, and special personnel shall be designated to carry out fire safety patrol.

During the “two festivals” and the Winter Olympic Games, the construction site shall be inspected continuously to prevent foreign fire sources from entering the construction site, and any fireworks and firecrackers found around the construction site shall be reported to the public security department in time.

At present, the construction sites of the city’s construction projects will gradually enter the state of shutdown in winter.

The district housing and Urban Rural Development Commission shall collect and summarize the “four accounts” of the construction site under its jurisdiction and submit them to the municipal housing and Urban Rural Development Commission.

The general contractor shall formulate the special plan for suspension and resumption of work of the project, specify the specific time of suspension and resumption of work, put forward the fully closed management measures of the construction site and the living guarantee measures for the left behind personnel during the suspension period, and formulate the on duty plan of the construction site during the suspension period and the emergency response plan for emergencies, Clarify the contact person and contact information on the construction site during shutdown, list the reserve list of emergency materials, formulate corresponding emergency response measures according to different types of emergencies, and organize and carry out an emergency drill.

The construction unit shall inspect the safety performance of temporary facilities such as enclosure, temporary houses and scaffolds on the construction site to ensure that they meet the requirements of wind and snow protection.

(II) self check the establishment of “four accounts”, and the construction general contractor shall establish the “four accounts” for the suspension and resumption of the project, including the project account, shutdown site account, construction site account and site resumption plan account within one kilometer around the Winter Olympic facilities, and report to the District Housing and Urban Rural Development Commission before the suspension.

Dangerous chemicals such as oxygen and acetylene shall be strictly classified and stored in a closed manner to prevent open fire from approaching.

(V) self check the fire safety management.

Those that cannot be cleaned temporarily shall be subject to fire isolation.

The construction unit shall clean up the combustibles on the construction site.

(III) self check the preparation and implementation of the special plan for suspension and resumption of work.

(seven) self check the organization of the people leaving Beijing, advocate the local people to celebrate the festival, insist on “do not need to go out of Beijing”, do not go to the high-risk areas in China, especially the counties and city flags and the land border ports where there are more than 1 cases (including 1 cases) of local COVID-19 infected persons within 14 days.