Construction contract of the latest ancient building renovation project in 2022

Remake the platform, and add step stones, steep boards, watch columns, staff search breast boards, plastering the floor of Yonglu Road, and stomping Ruyi; 5.

VII.

♩~♫.

♪..

♩..

project payment: after signing the contract, Party A shall pay 20% of the contract price as advance payment within 3 days after Party B’s formal construction; 40% of the contract price shall be paid after most of the projects are completed; 35% of the contract price will be paid after the project is completed; The warranty deposit of the project is 5%.

♩~♫.

♩~♫.

The original paint surface of all wooden components shall be removed, cleaned, the off shelf wood shall be painted, the on shelf wood shall be painted (to achieve the effect of ink dot gold, but not gold), and the damaged wooden components shall be replaced.

♪..

♪~♬..

♪..

2.

IV Project quality standard the project quality standard must meet the qualification standard of the current national code for acceptance of engineering building decoration quality.

Completion date: September 5, 2015.

Replace the crisp alkali green bricks on the wall and repair the cracks on the wall; Refer to the project budget for the above materials.

♪~♬..

♩..

Commencement date: July 5, 2015.

♩..

Party B shall be responsible for all safety accidents caused in the construction, and all expenses incurred shall be borne by Party B.

♩~♫.

The contract will come into force after being signed and sealed by both parties.

♩~♫.

♩~♫.

♩♫.

♩..

♩♫.

At the end of the warranty period, Party A shall pay Party B the quality assurance deposit of the project (i.e.

If necessary, the construction site shall adopt enclosure and other measures.

I.

3.

♪~♬..

♪~♬..

♩~♫.

Step stones and steep slabs are added to the apron of Confucian temple; 4.

Demolition of the original roof ridge and roof tiles of Dacheng Hall of Confucian temple, and cleaning of the brick roof; Waterproof the whole roof, add mortar leveling layer, waterproof coiled material, lay bottom ash, lay tiles, caulk and replace damaged tiles.

♩~♫.

♪~♬..

♪..

♪~♬..

♩..

♩♫.

project overview: Project Name: renovation project of Dacheng Hall of Confucian temple in Dongming County project location: Dongming county (in the school yard of No.

♩~♫.

♪~♬..

♪~♬..

Share the ball and praise the ball..

VIII Effective date of the contract: July 4, 2015.

V Safe production Party B must carry out safe and civilized construction.

construction period: contract period: 60 calendar days.

1 In case of any dispute arising from this contract, both parties shall negotiate in time.

♩..

♩ Daily reading Study to nourish one’s nature.

Contracting method: contracting labor and materials 2.

For each day of delay, five thousandths (5 ‰) of the contract price will be fined, but the total amount does not exceed five percent (5%) of the contract price.

2 This contract is made in duplicate, with each party holding one copy.

♩~♫.

♩~♫.

♩~♫.

♪~♬..

Party B shall be responsible for the warranty within the defect period, and the expenses shall be borne by Party B.

Vi.

♩~♫.

♪~♬..

♩..

♪~♬..

♪~♬..

1 middle school in the original town) project contracting scope: 1.

IX Supplementary provisions.

Click the blue word to pay attention to us in case of emergency ~ the construction contract of ancient building repair project employer (Party A): Contractor (Party B): in accordance with the provisions of the contract law of the people’s Republic of China and the construction law of the people’s Republic of China, following the principles of equality, voluntariness, fairness and good faith, and in combination with the specific conditions of the project, both parties reach the following agreement.

The warranty period shall be calculated from the time when Party B completes the construction and hands it over to Party A for use.

Party A (seal): Party B (seal): legal representative: legal representative: or entrusted agent (signature): or entrusted agent (signature): July 22, 2015 ♪~♬..

If it cannot be solved, it can apply to Heze Economic Contract Arbitration Commission for arbitration or directly bring a lawsuit to the people’s court.

The penalty will be deducted from the last allocated project price as liquidated damages.

♪~♬..

♩~♫.

Warranty period: the three-year warranty period shall be in accordance with the current national standard “Regulations on quality management of construction projects”.

♩~♫.

No award or penalty will be given for completion on schedule.

♪~♬..

♩..

Plate Anchor

Contract price (fixed price) (in words): seven hundred and seventy thousand yuan only; RMB 770000.00; III.

5% of the quality assurance deposit of the project).

♩~♫.

We recommend a selection of beautiful articles to our friends every day, hoping to bring you a ray of peace after work.

If the negotiation fails, either party can apply to the superior competent department for mediation.

♪~♬..