6-hour uninterrupted construction! Cold winter in port city and hot fetters of green intelligent projects

Xct40u crane of XCMG, with water blue paint and silver frame, blew up the street in Washington, USA! XCMG’s latest qy25k5d-3 crane has five U-arms and a full extension of 42m..

Early in the morning, all preparations for PR4 reclaimer are ready.

Qinhuangdao coal phase IV gantry reclaimer reconstruction project is a project to meet the long-term development needs of green and intelligent port, which is conducive to improving the core competitiveness of the port.

With the command issued by the hoisting commander, all cranes are put into the busy and orderly hoisting work together.

Xca750 and qay650a were lucky to participate in the project as the main force, and staged a mechanical show with both safety and efficiency.

Under the command of the hoisting commander, xca750 and qay650a respectively lift a gate leg weighing 106 tons and slowly place it on the track; With the cooperation of the surveyors and constructors, the huge door leg was pulled by the rope and adjusted to the specified position required by the installation specification.

“The Construction Party attaches great importance to the safety work on site.

Due to its own structure, the gate leg and fixed beam of the reclaimer are self heavy and the structural size is also large, which increases the construction difficulty for the gantry lifting to a certain extent.

Rubber Recess Former

Recently, the lifting and reinforcement of the gate leg and fixed beam of Qinhuangdao Port coal phase IV gantry reclaimer was successfully completed in the beautiful Qinhuangdao.

After uninterrupted construction, the lifting of the gate leg and fixed beam of Qinhuangdao coal phase IV gantry reclaimer took 6 hours, and all the test data met the installation requirements.

How many people still stick to their jobs? Please speak freely in the comment area.

We cooperated tacitly on site and completed the project efficiently!” President Zhao zhengran of Tangshan said excitedly.

The lifting and reinforcement of PR4 reclaimer portal leg and fixed beam is the key construction node of the project, and the subsequent installation and commissioning will be carried out on the basis of this work.

The temperature was low on that day, but the working enthusiasm of the construction personnel was not affected at all, and all work was progressing smoothly.

XCMG’s 750 ton and 650 ton cranes have strong stability and high safety.

In the future, XCMG crane will contribute to more green intelligent projects and contribute its heavy power to green China and smart Manufacturing China! As the new year approaches, there are still a group of amiable and respectable builders fighting on the front line and making extraordinary achievements in ordinary posts.