Article 7 the standard bidding documents uniformly formulated by the Ministry of transport shall be used in the preparation of the bidding documents for general contracting.
Article 6 a general contractor shall meet the following requirements: (1) at the same time, it shall have the survey, design and construction qualifications suitable for the bidding project, or a consortium composed of survey, design and construction units with corresponding qualifications; (2) having the financial capacity appropriate to the bidding project and meeting the conditions and requirements on survey and design, construction capacity, performance, etc.
The selection of bid evaluation experts shall comply with the provisions of relevant laws and regulations.
Article 2 These Measures shall apply to the general contracting of the design and construction of new construction, reconstruction and expansion projects of highways and independent bridges and tunnels (hereinafter referred to as highway projects).
Double Head Lifting Pin Anchor
The project legal person may determine the scope of general contracting according to the actual situation of the project.
Article 12 the project legal person shall sign a general contract with the bid winner.
put forward in the bidding documents; (III) in case of bidding by consortium, the leading unit shall be reasonably determined according to the characteristics and complexity of the project, and the responsibilities and rights of the member units of the consortium shall be clearly defined in the Consortium Agreement; (IV) the general contractor (including the member units of the general contracting consortium, the same below) shall not be the preliminary design unit, agent construction unit, supervision unit or the affiliated unit of the above units of the general contracting project.
Conduct credit evaluation on the general contractor in accordance with relevant regulations.
The general contracting of design and construction (hereinafter referred to as the general contracting) mentioned in these Measures refers to the contracting method in which the construction drawing survey and design, engineering construction and other engineering contents of highway engineering are uniformly implemented by the general contracting unit.
If the tenderee specifies in the bidding documents that the successful bidder has the right to use the technical scheme of the unsuccessful bidder, it shall generally specify the corresponding cost compensation at the same time.
shall be clearly stipulated.
Chapter II selection of general contractor and contract requirements Article 5 the general contractor shall be determined by the project legal person through bidding according to law.
The competent department of transportation shall supervise the implementation of laws, regulations, rules and mandatory standards by relevant parties to the general contract, and manage the preliminary design, construction drawing design, design change, etc.
The tenderee shall, according to the actual situation of the project, put forward the specific requirements for the tenderer to provide the technical scheme of construction drawing design in the tender document.
In the bidding documents for general contracting, the bidding contents, qualification conditions of bidders, quotation composition, contract duration, relevant requirements for subcontracting, survey, design and construction technical requirements, quality grade, project repair requirements in defect liability period, insurance requirements, cost payment methods, etc.
(Order No.
The bidding for general contracting of highway projects shall be carried out after the preliminary design documents are approved and the construction funds are confirmed.
Minister Yang Chuantang June 26, 2015 general principles of Chapter I of the general contracting management measures for highway engineering design and construction article 1 in order to promote the integration of highway engineering design and construction, improve the quality of highway engineering design and construction, and promote modern engineering management, these measures are formulated in accordance with relevant laws and administrative regulations.
The general contracting can implement the overall general contracting of the project, the general contracting can also be implemented by road sections, or the professional general contracting can be implemented for traffic Electromechanical, housing construction and greening projects.
Article 11 The tenderee shall determine the bid evaluation method according to the engineering geological conditions, technical characteristics and construction difficulties.
Article 10 the tenderer shall reasonably determine the preparation time of the tender documents, which shall not be less than 60 days from the date of sale of the tender documents to the deadline for the submission of the tender documents by the tenderer.
Article 4 the competent transportation departments at all levels shall be responsible for the supervision and administration of the general contracting of highway projects according to their duties.
The tender document shall include the following contents: (1) optimization suggestions for preliminary design; (II) project implementation, design and construction schedule; (III) special projects to be subcontracted; (IV) quotation list and description; (V) the technical scheme of construction drawing design provided according to the requirements of the tenderee; (6) if the bid is submitted by a consortium, the Consortium Agreement shall also be submitted; (VII) commitment to legally insure relevant engineering insurance in the joint name of the project legal person and the general contractor.
The legal person of the project is responsible for organizing the General Contracting Bidding of highway engineering.
10 of the Ministry of transport of the people’s Republic of China, 2015) administrative measures for general contracting of highway engineering design and construction, which was adopted at the 8th ministerial meeting on June 19, 2015, is hereby promulgated and shall enter into force as of August 1, 2015.
Article 3 the State encourages qualified highway projects to implement general contracting.
Article 13 the project legal person and the general contracting unit shall agree on the reasonable sharing of general contracting risks in the bidding documents or contracts..
Article 9 the bidding documents for general contracting shall be prepared in accordance with the requirements of the bidding documents in combination with the geological conditions and technical characteristics of the project.
The bid evaluation committee shall include survey, design, construction and other experts, and the total number shall not be less than 9.
Article 8 the general contracting tender shall provide the tenderer with preliminary design documents and corresponding survey data, as well as relevant reply documents and preliminary consultation opinions of the project.