(6) The temporary changes, oral instructions, meeting research and correspondence of the owner or the supervision unit shall be collected in time and sorted into words.
Three stages of claim (1) all construction managers should pay attention to the claim and know the claim.
Today we will bring you those things about claims.
3 force majeure and force majeure should be paid attention to (1) do not ignore the external environmental impact such as disastrous climate, discovery of underground obstacles, soft foundation or cultural relics, land acquisition and demolition, construction conditions, etc.
It should be considered as carefully as possible, the wording should be rigorous, and the rights and obligations should be clear, so as to achieve equality and mutual benefit.
(1) after winning the bid, the construction enterprise should sign the construction contract with the employer in time and carefully.
The invincible principle of claim: the claim documents shall be carefully prepared on time and reasonably.
Learn the faithful record from the court trial recorder (1) during the construction process, the Contractor shall adhere to the written instructions of the supervisor and the owner.
(2) The contract price should preferably be adjustable.
The first point of claim: the first point of economic interest claim: the claim work is related to the economic interests of the construction enterprise.
When signing the contract, you have to be careful.
In actual engineering projects, there are still a lot of work within the scope of claims, and there are many rules for claims.
Please note the secret code “Ji Zhibao” when adding..
(7) Where new materials, new processes and new technologies are used for construction and there is no corresponding budget quota pricing, relevant cost information shall be collected or opinions of relevant cost departments shall be consulted to prepare the basis for settlement.
(2) The owner requires to change the local size and quantity of the construction project, adjust the construction materials, change the construction technology, etc.
If there is infringement, please contact and delete it.
In short, the claim work shall be reasonable, reasonable and timely, and “reasonable” can go all directions and “reasonable” can be carried out, “On time” can not fail.
(3) Water and power cuts exceed the time limit specified in the original contract; The construction is delayed due to the requirements of the construction unit or the supervision unit, resulting in project rework, slowdown, increase of quantities, etc.
Predictive analysis shall be carried out in time during construction to find the divisional and subdivisional works that may have claims.
The content comes from online articles, which are only for sharing and not for commercial use.
(4) Detailed records shall be made on the water cut-off, power failure, mobilization time, quantity, quality, etc.
Collect data before commencement (1) study the drawings.
(8) If the design or construction scheme needs to be changed during construction, the modification and supplementary visa shall also be made in time.
The claim items proposed shall be in line with the reality, the content shall be substantial, the evidence shall be conclusive and persuasive, the claim calculation shall be accurate, and the claim shall be handled in strict accordance with the provisions and procedures of the claim.
Thank you ▽ long press the QR code below to identify ▽ add Ji Xiaobao’s little assistant to get acquainted with the big guys in the industry ▽ the latest information of the government has skyrocketed in network resources ▽ vision is ahead of peer online and offline training ▽ Jizan lucky draw Fuli will immediately join Ji Zhibao’s official wechat group.
2.
Engineering visa is an important content of claim, and design change is an important basis of claim.
Relevant data shall be collected before the commencement of the project, including the traffic conditions of the project site, three supplies and one leveling, and whether the water supply and power supply meet the construction needs? Does the price of water and electricity exceed the budget price? Height of groundwater level, soil condition, whether there are obstacles, etc.
Even if it is necessary to execute its oral orders under special circumstances, it shall immediately require it to confirm in written documents or send a letter to the supervisor and the owner for confirmation.
(3) In case of on-site loss, on-site camera and video recording shall also be done to achieve the integrity of the data.
(3) The claim work runs through the whole process of construction.
(2) The claim must be fully justified, the evidence is conclusive, visa on time and pay attention to negotiation skills.
(2) Make construction logs, technical data and other construction records.
(9) In case of industrial injury and mechanical accident during construction, the actual situation of the site shall also be recorded in time to distinguish responsibilities; For idle personnel and equipment, delay in construction period and damage to the project, visa procedures shall be handled in time.
And clarify the policies, basis and methods of additional adjustment of contract price and claim, so as to provide contract basis and legal guarantee for adjusting project cost and claim during completion settlement.
(2) Organize professional technicians to carefully study the construction drawings, communicate with each other, and find out the omissions, errors, unknown, unknown, inconsistent with reality, conflicts between disciplines and other problems in the drawings.
(5) The visa procedures for design change, technical verification, increase and decrease of quantities shall be complete to ensure the integrity of data.
4.
Seven skills of claim 1.
of materials provided by Party A.
If necessary, the construction process can also be photographed or videotaped.
(3) In the joint review of drawings, the minutes of joint review of construction drawings shall be carefully made.
Claim is an international engineering term.