The relevant inspection (Annex 5) shall be submitted to “Qingdao construction safety supervision station” through Jinhong on May 25..
Do a good job in flood prevention of housing construction projects under construction this year, The task of ensuring economic and social security development is arduous and of great significance.
It is necessary to formulate the emergency evacuation disposal plan for personnel in flood season, implement the emergency resettlement sites in advance, and timely organize the orderly evacuation of personnel in case of major flood, so as to ensure the life safety of employees in flood season.
Focus on strengthening flood season management and continuously improve the ability of emergency response.
The self inspection and self correction of potential safety hazards before flood season of all relevant units and projects (see Annexes 1, 2, 3 and 4) shall be scanned into electronic format after being stamped with the official seal of the project construction, construction and supervision unit, and sent to the construction safety supervision organization of the project location before May 25.
At the same time, they shall strictly enforce the discipline of flood control work, strengthen accountability, and ensure the implementation of all work and achieve practical results.
In order to further implement the deployment and arrangement of flood control work at the central, provincial and municipal levels, according to the requirements of the notice on making preparations for flood control in 2022 (qingxunshan [2022] No.
II.
Each district and municipal construction safety supervision organization shall inspect and supervise the investigation and rectification of potential safety hazards before the flood season, and establish a standing book of major potential safety hazards in the flood season.
35) issued by Qingdao Municipal Bureau of housing and urban rural development.
From now until May 31, all relevant units and housing construction projects under construction shall immediately carry out a pre flood safety hazard investigation, self inspection and self correction, adhere to the principle of “fundamentally eliminating accident hazards and fundamentally solving problems”, comprehensively find out the sources of safety hazards in flood season on the construction site, highlight the key contents, and organize the investigation of deep foundation pit, temporary facilities, scaffold, formwork support Conduct in-depth investigation and rectification of key parts and key links such as construction hoisting machinery and retaining wall, establish rectification standing book for hidden dangers and problems found, implement rectification measures, clarify the responsible personnel, track the rectification situation in time, and ensure that hidden dangers and weak links are found in the inspection, the causes of hidden dangers and weak links are not clear, the responsible person is not clear, and the rectification measures are not implemented, Ensure that every house construction project under construction, every part and every link are inspected and rectified in place, and resolutely put an end to the problem of “entering the flood season with disease”.
All housing construction projects under construction shall strictly implement the provisions on the preparation, inspection, commissioning and maintenance of flood control emergency materials and equipment, clarify the person in charge of flood control, and post the emergency duty list in flood season to ensure that all flood control work can be carried out quickly and orderly when the flood comes, The emergency plan shall be filed in accordance with the relevant requirements of the notice on the management of emergency plan for production safety accidents in the field of housing construction projects under construction (qjgz [2021] No.
Strive to improve ideological understanding, The responsibility of flood control work is closely organized in an all-round way.
All units shall closely organize the work responsibilities at all levels according to the relevant requirements of flood control work, compact and compact the specific responsibilities level by level, project by project and post by post, effectively run the responsibilities through the whole process of flood control work, and realize the full coverage of responsibility implementation.
Notice on strictly and strictly carrying out the investigation and rectification of potential safety hazards before the flood season of housing construction projects under construction in 2022 all district and municipal construction safety supervision institutions, Qingdao West Coast new area construction project management service center and relevant units: 2022 is the year of the 20th National Congress of the Communist Party of China and the key year for the implementation of the 14th five year plan.
All units should proceed from reality, adhere to the problem orientation, carefully summarize the experience and lessons of flood control in recent years, compare the problems exposed in the response to major flood disasters such as the “7.20” rainstorm disaster in Zhengzhou, combined with the actual situation of construction, solidly do a good job in pre flood safety management, and timely revise and improve various plans and schemes, Further clarify the responsibilities and tasks, refine the disposal process, effectively enhance the pertinence, scientificity and operability of the plan, carry out flood control emergency drills in combination with the contents of the plan, continuously improve and standardize the operation process of the plan, ensure the efficient emergency response of the plan, and continuously improve the flood control emergency disposal capacity of housing construction projects under construction.
It is an important work to ensure development and keep the bottom line.
1) and other documents issued by Qingdao flood control and Drought Relief Headquarters, the relevant requirements for organizing the investigation and rectification of potential safety hazards before the flood of housing construction projects under construction in 2022 are notified as follows: 1.
focus on the key contents, and promote the investigation and rectification of hidden dangers before the flood season.
At the same time, organize the employees on the construction site to carry out a comprehensive flood control emergency safety education, training and drill before the flood season, so as to ensure that all employees fully master the contents of the plan and are familiar with the plan process.
Recently, the rainfall in many places in the South will reach the strongest period since the flood season, and the local rainfall may break through the extreme value of the same period in history.
In summer, affected by typhoon going north, the situation of flood and typhoon prevention is still severe.
In recent years, affected by global climate change, extreme weather such as typhoons and heavy rainfall have occurred frequently, especially the “7.20” rainstorm disaster in Zhengzhou, Henan Province last year.
III.
Flood control work is related to the safety of people’s lives and property and the overall situation of social and economic development.
All units should promote the investigation and rectification of hidden dangers of housing construction projects under construction before the flood season in combination with the current major inspection of safe production in the field of housing and construction in the city.
According to the prediction of meteorological and marine departments, the meteorological situation of our city in 2022 is complex and changeable, and local heavy rainfall, rainstorm and flood disasters may occur.