The notice shows that the design approval of Shenzhen Huizhou intercity Dongguan section has not been completed and the engineering quality supervision procedures have not been handled, but the substantive construction of shield structure working wells and other work sites has been carried out, It does not conform to the railway capital construction procedures, the work safety law and the spirit of the national work safety teleconference on March 31, 2022.
The full text of the notice is as follows ▼ Dongguan rail transit Bureau and Shenzhen Metro Group: Recently, we received a letter from Dongguan rail transit Bureau on clarifying issues related to the early commencement of the project from Shenzhen Huizhou intercity Qianhai free trade zone to Ping section (Dongguan section) (Dongguan letter [2022] No.
🏃🏃🏃* If you have anything to say, please leave us a message* 👀 Editor: Nandu reporter zhangyanli editor: Yu Simin has more exclusive materials.
Please follow them.
1、 The Shenzhen Huizhou intercity Dongguan section has not completed the design approval and has not gone through the engineering quality supervision procedures, but has carried out substantial construction of shield working wells and other construction sites, which is not in line with the railway capital construction procedures, the work safety law and the spirit of the national work safety teleconference on March 31, 2022.
A man in Shenzhen had cerebral hemorrhage in the early morning and was sent to hospital urgently! These bad habits should be changed quickly to see more important things in Shenzhen in the lower left corner.
✪ 4 new cases! Shenzhen reported the latest situation of the epidemic situation: it was found in the investigation of personnel from other provinces who came to Shenzhen that ✪ they stayed up late to brush their mobile phones.
The project construction unit shall promptly improve the project construction procedures to ensure that the project is constructed in accordance with the law.
247), reflecting that the project from Shenzhen Huizhou intercity Qianhai free trade zone to Ping section (Dongguan section) violates railway infrastructure procedures Construction before approval.
Today (April 18), the Department of transportation of Guangdong Province issued a notice on ordering the suspension of construction in the Zhiping section (Dongguan section) of Shenzhen Huizhou intercity Qianhai bonded zone.
3、 The administrative supervision of the construction of Shenzhen Huizhou intercity Dongguan section project shall be handled in accordance with the national, provincial and Dongguan municipal regulations, and the specific matters of quality supervision and work safety supervision shall be clarified separately.
The construction unit is hereby ordered to suspend the construction of Shenzhen Huizhou intercity Dongguan section from now on.
In this regard, the following requirements are put forward.
Click below to follow us ▽✪ free tickets! Here in Shenzhen, a sea of flowers covering an area of 8000 ㎡ is blooming, and your appearance is amazing! The flowering period will last until…
2、 Shenzhen Metro Group shall urge and organize all participating units to carefully study and implement the management requirements of safety production and capital construction procedures, and do a good job of safety patrol and protection during the shutdown period.
Just “like” and “watching” them! 👇👇。.
The construction unit is hereby ordered to suspend the construction of Shenzhen Huizhou intercity Dongguan section from now on.