The second phase of Intelligent Manufacturing Industrial Park is busy with construction

The earthwork backfilling of B5 and B6 power houses has been completed, and the concrete pouring of foundation short column has been completed.

In the next step, the Industrial Company of the new area will continue to increase security, strengthen supervision and implementation, and closely coordinate and contact to ensure that the construction work is completed with high quality, efficiency and on schedule, and provide a platform for the transformation and maturation of important scientific and technological achievements for the construction of helingel talent science and innovation center.

At present, the earthwork backfilling and cushion concrete of B1 plant have been completed.

Earthwork backfilling and ground beam concrete pouring of B2 and B3 power houses have been completed.

At present, the Intelligent Manufacturing Industrial Park Phase II bid section I project has obtained the construction license and is under intensive construction.

Halfen Frimeda

The Industrial Company of the new area and all participating units will continue to be inspired, innovative and practical, and run out of the “acceleration” of the construction and development of the new area.

Within the year, all the individual main bodies of the phase II bid section I have been capped, and the facade construction and the external network works of the main road section have been completed.

The first section of phase II of the intelligent manufacturing industrial park has a total construction area of 30000 square meters, with a total of 5 standardized intelligent manufacturing plants (B1, B2, B3, B5, B6) and 1 multi energy complementary energy center.

Source: financial media center, Helingeer new area, Inner Mongolia..

In the construction progress of the multi energy complementary center, the drilling exploration and groove inspection of the B5 plant have been completed, and the greening and ground hardening of the north side of the office area have been completed.

Click on the top to focus on the Intelligent Manufacturing Industrial Park as an important carrier for Helingeer new area to carry the transformation of scientific and technological achievements of the autonomous region.

The concrete pouring of the beam slab column wall in the basement of the multi energy complementary center of the project has been completed, the waterproof construction of the external wall, the waterproof protective layer, the earthwork backfilling and the ground cushion have been completed.