The construction of Zhaodong service area will start in August!

Build a new culvert of 11.5m.

Borrow earthwork: 29611m of the main line ³、 Site 105961m ³, 135572m in total ³。 Greening 19336 ㎡.

A total of 28174 ㎡.

Are you looking at me?..

Lifting Loop

Including: WiFi coverage system in the service area, display system of remaining parking spaces in the service area, smart toilet, and indoor information release screen.

If there is infringement, please contact this platform in time, and we will delete the relevant content as soon as possible.

Borrowed earth: main line 31935m ³、 Site area 54748m ³ 86683m in total ³。 The greening area is 19038 ㎡.

2.4 planned construction period: August 15, 2022 to July 31, 2023.

F2 the k550+000-k551+509 complex building in Daqing Harbin direction of suimen expressway is 2054.79 square meters, and the auxiliary room is 323.68 square meters, which is a frame structure.

Source: Heilongjiang Provincial Development and Reform Commission tip: if the source of the content published in this official account is indicated, the copyright belongs to the original source.

Pavement: 3438 ㎡ of main line, 4515 ㎡ of ramp, 24433 ㎡ of site, a total of 32386 ㎡.

Pavement: 4367 ㎡ main line, 4905 ㎡ ramp and 18902 ㎡ site.

A 34m prestressed concrete bridge and a 11.5m culvert will be built.

According to the heifa gaijiao Tong [2021] No.

2.3 bid section division: it is divided into three bid sections.

The uplink service area is located in the range of k546+200-k548+300, and the downlink service area is located in the range of k550+000-k551+509.

The uplink service area covers an area of 52825 square meters, with a construction area of 3829.48 square meters; The downstream service area covers an area of 35101 square meters, with a construction area of 2378.47 square meters.

2.2 bidding scope: Construction and defect liability repair of housing construction, site area, acceleration and deceleration lanes, bridges, culverts, traffic safety facilities, electromechanical, greening and other works of the project.

Relevant information is as follows: 2.1 project overview: the project is located in Jiangjia town and Zhaodong town of Zhaodong City, on both sides of Harbin Daqing section of Suiman expressway.

The communication system includes: optical fiber digital transmission system, communication power supply system and optical cable engineering.

The main works of the bid section are shown in the following table: location of the bid section, main works and quantities F1, 3453.78 ㎡ of k546+200-k548+300 complex building from Harbin to Daqing of suimen expressway, 375.7 ㎡ of auxiliary rooms, frame structure.

Four 1256m acceleration and deceleration lanes and ramps, one 34m small bridge and two culverts are set; The service area is arranged in a separated asymmetrical way, covering an area of 87926 square meters and a building area of 6207.95 square meters.

There are 17.5m original culvert extensions.

The original culvert is extended by 16.2M.

591 document issued by the development and Reform Commission of Heilongjiang Province, the Zhaodong service area project of Harbin Daqing section of suimen expressway is about to start.

350 calendar days in total.

Smart service area.

F3 Suiman Expressway from Harbin to Daqing k546+200-k548+300, Suiman Expressway from Daqing to Harbin k550+000-k551+509 high-voltage line tower anti-collision body, corrugated beam steel guardrail, fence and anti falling net on both sides of the expressway, fence around the service area, traffic signs, markings, communication and power manholes and pipelines.