From October 29, this section of Jiangdong Avenue will be closed for construction. Please drive slowly!

In case of violation, punishment will be imposed in accordance with the Road Traffic Safety Law of the People’s Republic of China and relevant laws and regulations.

The third stage: construction time (February 1, 2023 to March 20, 2023) The east side of Jiangdong Avenue (Chengzhong Road to Jiangdong 1st Street) will be closed to a roadway, and the west side will be two-way.

Precautions: All drivers and pedestrians should consciously abide by the laws and regulations on road traffic safety during the construction, follow the instructions of construction billboards and traffic signs, and obey the command of on-site management personnel.

Phase VI: construction period (February 15, 2023 to August 25, 2023): sidewalk construction of Jiangdong Avenue (Jiangdong Fourth Street – Chengzhong Bridge Section), with pedestrians and non motor vehicles passing on the right side of the road.

Three traffic restrictions and detour plan Phase I: construction time (October 29, 2022 to December 15, 2022).

The relevant matters are hereby announced as follows: 1.

▲ During the construction period, please try your best to stagger the peak to avoid traffic congestion.

The time limit is from October 29, 2022 to August 28, 2023.

The fifth stage: the construction time (June 1, 2023 to July 31, 2023): the east side of Jiangdong Avenue (Jiangdong 1st Street to Jiangdong 4th Street) will be closed and the west side will be two-way.

The entrance and exit of the hotel on the north side can temporarily pass, and pedestrians, non motor vehicles and motor vehicles can walk on the sidewalk; Pedestrians and non motor vehicles on the south side can walk along the sidewalk to the city bridge.

IV.

The second restricted section is Jiangdong Avenue (Jiangdong 4th Street to Chengzhong Bridge).

It is hereby announced! Jiangshan Urban Development Investment Co., Ltd.

Peri Prop Nut

Jiangshan Public Security Bureau Traffic Police Brigade October 25, 2022 Source: Jiangshan Traffic Police Editor: Mao Xuexi Reviewed by: Zheng Xiaolin..

The fourth stage: construction time (March 21, 2023 to May 30, 2023) The west side of Jiangdong Avenue (Jiangdong 1st Street to Jiangdong 4th Street) will be closed, and only one roadway will be reserved for north to south traffic, one-way traffic; South to north by sidewalk.

The second stage: construction time (December 10, 2022 to January 20, 2023) The west side of Jiangdong Avenue (Chengzhong Road to Jiangdong 1st Street) will be closed, and only one roadway will be reserved for north to south traffic, one-way traffic; South to north by sidewalk.

Notice on the Implementation of Traffic Restriction Measures during the Construction of Jiangdong Avenue (Jiangdong Fourth Street – Chengzhong Bridge Section), Jiangdong New Town Road Network, Rainwater and Sewage Pipe Network and Other Supporting Facilities Construction Project, Jiangdong Avenue (Jiangdong Fourth Street – Chengzhong Bridge Section), According to Article 39 of the Road Traffic Safety Law of the People’s Republic of China, it is decided to implement traffic restriction measures on Jiangdong Avenue (Jiangdong Fourth Street – Bridge in the City).

The section of Chengzhong Road (Jiangbin East Road to Jiangdong Avenue) will be fully closed.