What is the cost of safe and civilized construction?

Details of safe and civilized construction costs are as follows: 1.

Details of bulletin boards and safety signs: (1) bulletin boards, operation specification boards, post responsibility boards, management system boards, safety sign boards, bulletin boards, newspaper reading boards, safety posters, safety slogans, and electronic displays; 4、 Details of temporary facilities: 1.

Details of other protective facilities: (1) electric saw protective plate, cutting machine protective plate; (2) Tower crane protective fence, tower crane anti climbing facilities, outdoor elevator scaffold (including warning signs, interlayer safety doors, protective sheds); (3) Anti smashing shed, safety protection channel, standard catwalk in foundation pit; (4) Tower crane testing fee, outdoor elevator testing fee, electric basket testing fee; 3.

Environmental sanitation fee for toilets at the construction site and workers’ living quarters (floor tiling, urinal tiling, external wall painting, ultraviolet fly killing lamp, daily washing fee); 6.

Hardening of construction site, office area and workers’ living area (road hardening, site hardening, drainage ditch, pit berm hardening); 4.

Afforestation cost and security facilities (green planting cost, alarm equipment, monitoring equipment, security room and security equipment) for construction site, office area and workers’ living area; 8.

Details of temporary construction facilities in the project office area: (1) offices, dormitories, meeting rooms, canteens and dining areas, toilets, showers, flagpoles, flag stands, recreation rooms, sports facilities; 3.

Foot Eye Anchor

Materials storage facilities on the construction site (ordinary materials warehouse, toxic and harmful materials warehouse, reinforcement processing shed and reinforcement yard, woodworking shed and formwork timber yard, water and electricity processing shed and water and electricity materials storage yard, bulk cement tank, dry mixed mortar tank, material identification signs); 5.

2、 Details of civilized construction cost: 1.

Site enclosure facilities (site enclosure, nine boards and one drawing, enclosure plate brushing VI or pasting advertising cloth (artificial turf), and lighting fixtures on the enclosure top); 2.

Details of temporary power facilities: (1) primary distribution cabinet and switch box, secondary distribution box and switch box, distribution lines, lighting fixtures, grounding protection devices, distribution room, external power protection facilities, emergency lighting, cable sleeves; 5.

Details of temporary construction facilities in workers’ living quarters: (1) offices, dormitories, meeting rooms, canteens and dining areas, showers, toilets, smoking areas, water boiling rooms, parking sheds, night schools for farmers and workers; 4.

Cover cost of bare soil filter screen at the construction site (including filter screen material cost); 3.

3、 Details of safety construction cost: 1.

On site washing facilities (car washing tank, sedimentation tank, sewage tank) for muck trucks, concrete tankers and garbage trucks; 5.

Construction site environmental monitoring system.

Dust reduction facilities (sprinkler, fog monitor, on-site spraying system, mortar grouting dust protection, daily watering fee, daily road cleaning fee); 4.

Details of fire protection facilities: (1) fire hydrant, fire pool, fire water pipe, fire box, extinguisher, fire pump room, fire hose, fire equipment concentration place, smoke alarm device; 5.

The cost of safe and civilized construction is a total price measure cost in the construction and installation cost.

2.

Medical first-aid expenses (medical kits, stretchers, training videos, medical first-aid manuals); 9.

Now the new budget consumption standard is implemented, and the safe and civilized construction cost needs to be quoted independently when bidding.

Epidemic prevention fee (mask, nucleic acid detection fee, epidemic prevention material fee, isolation room, temperature measuring device, daily disinfection and sterilization fee).

Details of vertical, horizontal and edge protection facilities: (1) “four entrances” protection facilities (guardrail at the stairway entrance, guardrail at the elevator entrance, guardrail at the passageway entrance, and guardrail at the reserved entrance); (2) “Five edge” facilities (balcony fence, floor fence, roof fence, pit fence, and both sides of the unloading platform); (3) External wall protective scaffold, cantilever frame, climbing frame, elevator shaft protective platform, anti falling net, protective net; 2.

Details of temporary construction facilities on the construction site: (1) office, process sample area, material sealing display board, material exhibition room, tea room, smoking area, three-level education platform, site safety experience area, weighbridge.

Details of temporary water facilities: (1) Temporary simple water tower, water tank, temporary water supply pipeline and temporary drainage pipeline..

Before the implementation of the Beijing Construction Project Pricing Basis – Budget Consumption Standard and the Beijing Housing Repair Project Pricing Basis – Budget Consumption Standard in 2021, when the safe and civilized construction cost is used as a non competitive cost for bidding, the pricing software will directly charge for it.

The cost includes four parts: environmental protection cost, civilized construction cost, safety construction cost and temporary facilities cost.

Sewage facilities at the construction site, office area, workers’ living quarters, sewage charges (septic tank, oil separator, daily fecal pumping costs); 7.

This requires us to have a more detailed understanding of the detailed costs of safe and civilized construction.

Heatstroke prevention fee (air conditioner, electric fan, Huoxiang Zhengqi Water, essential balm); 10.

Living facilities at the construction site, office area and workers’ living area (wash basin, washing basin, clothes rack, clothes drying shed, charging pile, charging cabinet, water heater, water dispenser, door curtain, smoke alarm device); 7.

Details of environmental protection costs 1.

Centralized storage facilities for construction waste and garbage in living quarters at the construction site, and garbage clearing and transportation fees (garbage cans, garbage pools, waste pools, garbage cleaning trucks, daily construction waste fees, and daily domestic waste fees); 6.

Enclosed facilities at the construction site, office area and workers’ living area (site gate, enterprise logo, gate, face recognition access control system, on-site monitoring system); 3.

Noise reduction and prevention facilities (sound-absorbing steel vertical protective net, electric welding room, and sound insulation shed for ground pump operation); 2.

Details of safety supplies: (1) safety helmet, safety belt, safety net; (2) Labor protection gloves, insulating gloves, insulating shoes, rain shoes, raincoats; 4.