Scope of bidding: This bidding mainly includes the transportation guidance and reconstruction, the relocation of some municipal pipe networks and greening and other early works; The specific scope of bidding for civil works and depot works of stations, sections and main substations shall be subject to the bidding documents.
6.
Jinan Metro Line 7 is a north-south longitudinal backbone line, involving high-tech zone, Lixia District, Licheng District, overpass area and starting area.
Project name: General Contractor for Civil Engineering and Depot Construction of Jinan Rail Transit Line 7 Phase I Project Construction Unit: Jinan Rail Transit Group Construction Investment Co., Ltd.
The southernmost end of the line is located in Hanyu District.
At the intersection of Tourist Road and Fenghuang Road, it extends westward along Tourist Road and Long’ao South Road; Turn north from Zhuanshan West Road, pass the central axis of CBD core area and Chemical Fiber Factory Road, turn west to Huayuan Road, and enter the old urban area within the Second Ring Road; Then extend northward along Lishan North Road, Jiangjun Road and Daqiao Road, pass the Yellow River Bridge, and finally enter the starting area bridge area on the north bank of the Yellow River.
The total length of the line is about 30 km, with 22 stations…
4.
It is the only subway line extending to the north of the Yellow River in Jinan at present.
On November 21, Jinan Public Resources Trading Information Center released the prequalification announcement (on behalf of the bidding announcement) of the general contracting for the civil engineering and depot construction of Jinan Rail Transit Line 7 Phase I Project.
1.
3.
5.
Section division: the project is divided into 1 section.
Planned duration: 1826 calendar days (subject to the actual commencement and completion date).
Quality standard: qualified, meeting the national and relevant industry acceptance standards.
2.
Construction site: Jinan City; Project scale: about 30km.