The whole road section will be closed in the morning, and the flow regulation scheme will be released

375 meters of water supply pipes with a diameter of 300 mm are to be replaced, which is planned to be completed in one month.

② The Beizhao route goes from east to west to Taizhizhuang: turn right at the intersection of Beizhao Road and Lanwang Road → the intersection of Yangjiazhuang Village → namely Lan Road.

during construction, and formulates a low impact construction plan to ensure safety, less occupation of roads and disturbance to residents, fast construction and exit, smooth roads, smooth pipe networks, and green construction.

the section from Lan Road to Beizhao Road) will be widened and reconstructed.

Qing Baojun has learned that Jimo Liulong Road (i.e.

Traffic regulation scheme: ① Beizhao route goes from west to east to Taizhizhuang: turn left at the intersection of Beizhao Road and Lanwang Road → the intersection of Yangjiazhuang Village → namely Lan Road.

have been completed, and the whole road section will be closed from tomorrow.

It is reported that the original water supply pipeline of Liaoyuan Road has been in service for many years, and there are certain potential safety hazards.

The closing time is from March 10, 2022 to August 10, 2022, and the construction is totally closed.

In order to minimize the impact, Qingdao Water Group follows the basic principle of “safety, less occupation, fast return, smooth roads, open pipes, and green”, takes active and effective measures in terms of dust control, light pollution, construction noise, traffic regulation, etc.

④ That is to say, the Lanzhou route goes east to west to the direction of Tuanwan Village: turn left at the intersection of Jilan Road and Chenggezhuang Village → Yangjiazhuang Village Road → Beizhao Road.

The construction process will inevitably affect the production, life and travel of surrounding enterprises and residents.

At present, the construction organization design, traffic organization scheme review, design technical disclosure, installation of traffic regulation signs on the surrounding road network, etc.

In addition, Qing Baojun learned from Qingdao Water Affairs Hairun Waterworks Group that the reconstruction project of Liaoyuan Road water supply network will start on March 10.

With the increase of water consumption of surrounding residents, the original pipeline can no longer meet the water supply requirements.

Erection Anchor One Sided

generally known! Forward it to your friends who live nearby! ● Travel path of confirmed cases and asymptomatic infected persons of COVID-19 in Weihai City ● List of Fever Outpatients in Qingdao City (as of March 9, 2022) Reporter | Wang Tao, Wu Shuai, Editor | Taozi Source | Qingdao Daily (qddaily) comprehensive self viewing news client,.

③ Namely, the Lanzhou route goes west to east to the direction of Tuanwan Village: turn right at the intersection of Jilan Road and Chenggezhuang Village → Yangjiazhuang Village Road → Beizhao Road.

Liaoyuan Road Project starts from Shaoxing Road and ends at Cuopuling Second Road.

At present, all preparations have been put in place and we will strive to complete the construction task in the shortest time.

The closed section starts at the junction of Liulong Road and Taizizhuang Village, and ends at the junction of Liulong Road and Beizhao Line.

Jimo District will accelerate the progress of project construction, ensure that the project is completed and opened to traffic on time, and provide smooth and convenient traffic conditions for people to travel and the economic development of the whole district.