Construction content on April 19th

The roof of the 28th section of the garage will be poured, and the waterproof protective layer of, 8 general workers, 26 to 25 section garage roof cleaning, 6 general workers, external wall waterproofing base treatment of western-style houses, 1 general worker, 2 signal workers, 3 lifting workers, 8 building non motorized vehicle ramp steel bar binding, 3 steel workers, 22 section garage basement discharge, 5 general workers, 8 building secondary structural steel bar processing, 3 steel workers, 8 building 33rd floor laying out, 2 laying workers, 8 building roof waterproofing construction, 4 waterproof workers, 11 building elevator protection installation, 3 external processing personnel, 1 construction elevator driver, 11 firefighting personnel, and 21 project management personnel.
.

Waved Anchor

One worker will be responsible for adding block pouring materials to the second floor of the East Single Building.

Two workers will be responsible for the binding of steel bars on the roof of the Seventh Building.

Three workers will be responsible for setting up a passage for the material lifting machine of the First Building.

Four workers will be responsible for woodworking, and four workers will be responsible for reinforcing the formwork.

Phase 2: 6 management personnel, Two workers will be responsible for the second structure layout, and the third floor of the East Single Building will be discharged.

Four workers will be responsible for the reverse ridge formwork support of the second floor of the West Single Building.

Two workers will be responsible for the removal of steel pipes from the roof of the Second Building.

On April 19th, there were 38 construction content management personnel and 151 workers in Phase 1: 2 external wall management personnel in Building 9, 5 leveling personnel for the open balcony of Building 9, 5 external wall insulation personnel, 1 miscellaneous worker, 3 leveling personnel for the corridor, 2 external wall management personnel in Building 10, 2 secondary structure management personnel in Building 15, 2 putty workers in the corridor position, 3 construction personnel in the balcony sample room, 7 garbage cleaning personnel in the secondary structure floor, 9 plasterers, 1 plasterer, and 1 minor worker, There are 2 elevator drivers for Building 15, 2 putty workers on the north side, 2 loading workers, 4 putty workers on the south side, 4 putty workers on the balcony inside the building, 4 real stone lacquerers, 1 exterior wall management personnel for Building 12 and Building 16, 2 real stone paint for the exterior walls of Building 12, and 4 real stone paint for the exterior walls of Building 16.

There are 2 masonry personnel on the first floor of the kindergarten, 1 steel bar binding personnel, 2 steel bar planting personnel on the second floor, 1 formwork ingredient carpenter, and 2 protective door installation personnel.