Among them, Longao Station, Olympic Sports Center West Station, Ligeng Road Station, and West Zhoujiazhuang Station are fully enclosed construction.
Insert a good news: A new intersection will be born at 5am tomorrow on Jingshi Olympic Sports Middle Road! There is another even more exciting news: on June 17th, the R3 line officially started! However, starting construction means that there will be ten intersections (marked in the figure below) for fence construction.
Lu Mi, who often goes to the Olympic Sports Center to watch football, don’t forget to pay attention to our Jinan traffic police WeChat in a timely manner.
Vehicles to Jinan Procuratorate and Armed Police Detachment can enter and exit from the ramp at the Northwest Angle of Mengjia Interchange.
Shu Shu will release new pictures of the parking area for watching football as soon as possible.
The construction of Aoti West Road has the greatest impact, with the entire Aoti West Road almost losing its traffic function.
In addition, with the closure construction of Yanshan Interchange, Shu Shu suggests that friends in Dongcheng should drive less and adopt green transportation for travel.
At the same time, some lanes of roads such as Jingshi Road, Gongye South Road, Huayuan East Road, and Gongye North Road have been slimmed down.
(Although Shu Shu knows that your mood may not be good at all, considering the future of rail transit running all over the city, isn’t the pain in front of you a divine horse?) Longdongzhuang Station and Mengjiazhuang Station Time: From June 17, 2016 to March 31, 2018 Scope: Construction of partial lane closure on Longding Avenue, passing vehicles can bypass Olympic East Road or slowly drive according to signs and markings.
Vehicles heading towards Longao on the east side can bypass Aoti East Road; Vehicles on Olympic Middle Road can detour around Olympic East Road at the exit of the auxiliary road near Exit 7 of the Olympic Center.
Olympic Center West Station Time: From June 17, 2016 to January 31, 2018 Scope: Fully enclosed construction of Olympic West Road (Jingshi Road to Jiefang East Road section).
Li Geng Road Station Time: From June 17, 2016 to August 31, 2017 Scope: Fully enclosed construction of Aoti West Road (planned to be about 300 meters on both sides of Li Geng Road)
.
Wishing everyone safe travel and a good mood every day.
Bypass: Vehicles traveling around Long’ao West Road and Long’ao North Road.
Long’ao Station Time: From June 17, 2016 to January 31, 2018 Scope: Fully enclosed construction for approximately 500 meters on both sides of the intersection of Long’ao South Road and Aoti West Road.
The sections most affected are Aoti West Road, Gongye North Road, Longding Avenue, etc.
Bypass: During this period, the number of east-west lanes at the intersection of Jingshi Road remains unchanged, and the overall southward movement occurs.
(Do you still want to collect such a beautiful original high-definition large image?) Due to the involvement of too many roads and the significant impact on traffic, Shushu decided to nag a few words in advance.
Shu Shu predicts that a large wave of bypass vehicles are approaching Aoti Middle Road, Langchao Road, and Shunhua Road.