1、 Site construction operation (1) site mechanical equipment of work area I of project: 2 cement mixing piles, 2 cement mixing vertical tanks, 1 generator, 1 excavator, 1 blasting machine, 4 dump trucks; construction content: 700 m2 of concrete pavement at K0 + 300
.
Site stonework operation (2) site machinery and equipment in the second work area of the project: 5 cement mixing pile machines, 6 excavators, 4 dump trucks and 1 bulldozer; construction content: 625M m3 of internal earthwork for K1 + 560 ~ 580 section excavation and leveling; 40m of access road for K1 + 720 ~ 760 section and 400m2 of surface cleaning; 500m m3 of fish pond riprapping and silt squeezing for K1 + 840 section; 1200 m3 of soil pile for K1 + 940 ~ 750 section M2; 35 cement mixing piles in K1 + 290 ~ 300 section; 35 cement mixing piles in K2 + 020 section; 35 cement mixing piles in K2 + 145 ~ 150 section; 25 cement mixing piles in K2 + 150 ~ 170 section; 27 cement mixing piles in K2 + 250 section
.
The east side Subgrade of K1 + 960 ~ K2 + 010 section is excavated, and the earthwork is transferred to 450m3; the earth heap of K1 + 320 ~ 400 section is leveled about 200m2; the enclosure of K1 + 420 ~ 450 and K1 + 315 ~ 340 section is about 50m
.
Mixing pile driving operation 1 mixing pile driving operation 2 (3) project 3 site mechanical equipment: 1 excavator; construction content: K0 + 700 ~ 780 subgrade excavation of 1000 m2 to prepare for the construction of cement mixing pile
.
Site subgrade excavation II
.
Safe and civilized construction (1) morning class meeting (2) evening class meeting (3) civilized construction (1) disinfection and cleaning of project management department (1) civilized construction inspection I
.
civilized construction inspection II
.
Civilized construction inspection III
.
equipment and materials mobilization acceptance, application for inspection and submission for inspection 4 ᦇ cement tank mobilization 42.5 cement 30 tons ᦇ 5 ᦇ cement tank mobilization 42.5 cement 30 tons ᦇ second work area mobilization 80 cement piers ﹥ 14 DN 1000 cement pipes ﹥ 14 rubber rings ﹥ four major events of the project no five, tomorrow’s schedule work area I: K0 + 500 ~ 700 section site digging and leveling for cement mixing pile construction preparation; K0 + 300 section breaking cement pavement; mechanical input 2 digging machines Excavators, 1 gun machine and 3 dump trucks
.
Second work area: surface clearing and tree head excavation at K1 + 850, riprapping and silt squeezing at fish pond; construction of 4 cement mixing piles at Shenzhen No.20 senior high school section; earth excavation and internal transfer at the east side of K1 + 960 ~ K2 + 020 section; construction of cement mixing pile at K1 + 290 section; maintenance of access road at K1 + 450 ~ 550 section; laying of temporary drainage pipe at K1 + 310 section; earth excavation of Subgrade at K1 + 450 ~ 500 section; mechanical input of cement into the west side of K2 + 270 ~ K2 + 330 section There are 5 mixing pile machines, 6 excavators, 5 dump trucks and 1 bulldozer
.
Third working area: none.
.