1、 Daily temperature measurement
.
3、 Daily pre shift education
.
2
.
Formwork acceptance and concrete pouring for the north half of the second support beam on the second floor
.
3
.
The safety supervision station has been in the project to inspect and guide the work
.
4
.
Inspection of flood control materials
.
5
.
Chisel the contact surface between the supporting pile and waist beam at the north side of the second layer and the third bracing
.
On April 15, 102 vehicles were unearthed, with a total of 10308 vehicles, totaling 128850 square meters
.
4、 Follow up construction plan 1
.
Construction of the second support beam on the east side
.
2
.
The second layer of stonework is broken
.
3
.
Outward transportation of the second layer earthwork
.
5、 There is no need for the owner to coordinate
.