General contracting project (Lot 2) of medical complex building project of Longgang traditional Chinese medicine hospital project daily report on April 15, 2021

1、 Daily temperature measurement

.

3、 Daily pre shift education

.

2

.

Formwork acceptance and concrete pouring for the north half of the second support beam on the second floor

.

3

.

The safety supervision station has been in the project to inspect and guide the work

.

4

.

Inspection of flood control materials

.

5

.

Chisel the contact surface between the supporting pile and waist beam at the north side of the second layer and the third bracing

.

On April 15, 102 vehicles were unearthed, with a total of 10308 vehicles, totaling 128850 square meters

.

4、 Follow up construction plan 1

.

Construction of the second support beam on the east side

.

2

.

The second layer of stonework is broken

.

3

.

Outward transportation of the second layer earthwork

.

5、 There is no need for the owner to coordinate

.