Precautions for the construction of epoxy floor paint 1
.
The construction temperature is more than or equal to 5 ℃, and the humidity is recommended to be less than 75%
.
2
.
Ensure air circulation during construction
.
When modulating the usage, it should not exceed 30 minutes
.
3
.
The maintenance work should be done well during the construction process to avoid the invasion of dust and debris, which will affect the paint effect
.
4
.
After the completion of construction, it needs to be maintained for at least 7 days before it can be put into use
.
During the curing period, there should be no water or various solutions
.
5
.
Do not mix other paints
.
6
.
The curing agent must be added in strict accordance with the specified proportion
.
7
.
Keep the surface of the coating clean, and the moisture content of the coating must be less than 7%
.
8
.
Keep the painting environment clean and strictly prohibit the construction in the environment with a lot of dust
.