1、 Site construction operation (1) site machinery and equipment in work area 1 of project: 2 cement mixing piles, 1 cement mixing vertical tank, 1 generator, 1 excavator and 3 new energy dump trucks; Site construction content: 63 cement mixing piles were completed at mileage K0 + 140; 35 cement mixing piles were completed at mileage K0 + 670; Excavation earthwork of retaining wall foundation at mileage K0 + 580 turns inward for 600m ³; Reinforcement is installed on the bottom plate of communication cable gallery at mileage K0 + 090
.
K0 + 650 cement mixing pile construction K0 + 580 earthwork transfer (2) site mechanical equipment of the second work area of the project: 5 cement mixing pile machines, 6 excavators, 6 new energy dump trucks, 1 bulldozer and 1 roller; Site construction content: the excavation earthwork of foundation pit of rainwater tank culvert at mileage k1-880 is transferred to 320m ³, 23m concrete cushion for box culvert foundation of section K1 + 840 ~ K1 + 884 ³、 6
.
Installation of bottom slab reinforcement for box culvert; Y166 rainwater well is backfilled with 20 m stone powder ³; Access road at mileage K1 + 290: installation of W105 sewage well seat, excavation of temporary drainage ditch on top of foundation trench; 115 cement mixing piles have been completed in the section K1 + 940 ~ K2 + 370 of Shenzhen No.20 senior high school
.
K1 + 830 Box Culvert Reinforcement installation and K1 + 940 box culvert foundation concrete pouring (3) site machinery and equipment in the third work area of the project: 1 cement mixing vertical tank and 1 cement mixing pile machine; Site construction content: clean up the site garbage
.
Site garbage cleaning (4) mechanical equipment of temporary construction site of project department: 1 excavator, 1 bulldozer, 1 sprinkler; Site construction content: none
.
2、 Safe and civilized construction (1) morning class meeting (2) evening class meeting (3) civilized construction Safe and civilized construction inspection (1) Inspection of safe and civilized construction (2) 3、 Acceptance, application and inspection of equipment and materials Materials and reinforcement entering the site (1) materials and reinforcement entering the site (2) materials and reinforcement entering the site (2) materials and reinforcement entering the site of DN 165 cement pipe note: materials entering the site of Danzi North Road today are P.O 42.5 cement 30t, ﹥ 12 deformed steel bar 85.248t, ﹥ 14 deformed steel bar 53.724t, ﹥ 16 deformed steel bar 98.212t, ﹥ 20 deformed steel bar 10.67t, and 11 DN 165 water mud pipes; There are 4 pieces of DN 1650 cement pipes out of the site
.
4、 No major events occurred
.
5、 Tomorrow’s construction schedule work area I: Construction of cement mixing pile machine for mileage K0 + 140, K0 + 250 and K0 + 670 sections; The foundation of communication cable pipe gallery at mileage K0 + 090 is installed with reinforcement; Two excavators, three cement mixing pile machines and one excavator were put into operation
.
Second work area: Construction of cement mixing pile in section K1 + 940 ~ K2 + 370 of Shenzhen No.20 senior high school; W105-w106 sewage pipe installation and layered backfill stone powder tamping; The subgrade of y68 ~ y71 rainwater pipe is backfilled in layers, and the foundation trench of y140-y143 rainwater pipe is excavated and installed; The foundation pit of drainage box culvert at mileage K1 + 884 is excavated and backfilled with gravel base, and the bottom slab reinforcement of 6 × box culvert is installed; 5 cement mixing pile machines, 5 excavators, 4 new energy dump trucks and 1 road roller were put into operation
.
Third working area: none
.