1 [multiple choice questions] according to the code for valuation with bill of quantities of construction projects, the contract price of the project that is subject to public bidding includes ()
.
A
.
the contract price shall be agreed within 30 days from the date of issuance of the letter of acceptance B
.
the agreement on the contract price is the calculation and settlement method of the agreed project price C
.
the contract price shall be agreed in accordance with the bidding documents and the bid documents of the successful bidder D
.
the bidding documents shall prevail in case of any inconsistency between the bidding documents and the bid documents of the successful bidder e
.
the agreement on the contract price is the contract price of the construction project The main content of the same “correct answer” ace “answer analysis” this question examines the contract price agreement
.
Option B is wrong, because the contract price should be a specific amount, not a calculation and settlement method
.
In option D, the correct expression should be “in case of any inconsistency between the bidding document and the bid document of the successful bidder, the bid document shall prevail”
.
The following statements are correct when carrying out the measurement of quantities in the unit price contract construction
.
A
.
the project quantity measured by the supervising engineer is not necessarily the actual construction quantity of the contractor B
.
the insurance premium of the construction engineering insurance is generally measured by the equal share method C
.
The unit price contract is settled by the actual completed project quantity D
.
the supervisor must measure the project specified in the contract documents e
.
the supervisor may not measure the “correct answer” of the engineering change project ACD “answer” This question examines the measurement of unit price contract
.
Option B is wrong
.
The measurement methods generally include equal share method, voucher method, valuation method, section method, drawing method and decomposition measurement method
.
The insurance premium of construction engineering insurance is generally measured by voucher method
.
If option e is wrong, the scope to be measured by the supervisor includes: (1) all items in the bill of quantities( 2) Items specified in the contract documents( 3) Engineering change project
.
(3) for bidding projects, the date () days before the deadline for bidding, and for non bidding projects, the date () days before the signing of the contract
.
After the base date, if the change of law causes the increase of the expenses required by the contractor during the performance of the contract beyond the provisions of “adjustment caused by market price fluctuation” in the model text, the employer shall bear the increased expenses; In case of reduction, it shall be deducted from the contract
.
After the base date, if the construction period is delayed due to legal changes, the construction period shall be postponed
.
A.14, 14 B.14, 28 c.28, 28 d.28, 56 “correct answer” C “answer analysis” this question examines the adjustment of contract price caused by changes in laws and regulations
.
The tender project shall be 28 days before the tender deadline, and the non tender project shall be 28 days before the contract signing
.
The following statement about contract price adjustment caused by early completion is correct
.
A
.
when contracting out the project, the construction period compressed by the bid inviting party shall not exceed 20% of the approved construction period
.
If the construction period exceeds 20%, it shall explicitly increase the cost of speeding up the project in the bidding documents
.
B
.
the cost of speeding up the project mainly includes the enterprise management fee
.
C
.
if the contract project is required to be completed ahead of schedule by the employer, the consent of the contractor is not required
.
D
.
if the contract project is required to be completed ahead of schedule by the employer, The employer shall bear the Contractor’s increased expenses for early completion (compensation for rush work)
.
This question examines the adjustment of contract price caused by early completion
.
In option a, the correct expression should be “when the project is contracted out, the construction period compressed by the bid inviting party shall not exceed 20% of the fixed construction period
.
If the construction period exceeds 20%, the cost of speeding up shall be explicitly increased in the bidding documents”
.
In option B, the correct expression should be “the cost of rushing to work mainly includes; The increase of labor cost, material cost and machinery cost
.
Option C, the correct expression should be “if the employer requires the contract project to be completed ahead of schedule, the Contractor’s consent shall be obtained”
.
5 [multiple choice questions] the following descriptions about the determination of project change price are correct
.
A
.
the cost of safe and civilized construction shall be adjusted according to the actual change of measure items, which can be floated; B
.
if there are the same items in the priced bill of quantities, it shall be recognized according to the unit price of the same item; C
.
the floating factor of the Contractor’s quotation shall be considered in the adjustment of the cost of total price measure items; D
.
if there are similar items in the priced bill of quantities, the cost of the same item shall be recognized according to the unit price of the same item, Referring to the unit price of similar projects, e
.
the price adjustment caused by the change shall be included in the latest progress payment, and BCDE “correct answer” and “answer analysis” shall be paid
.
Option a, the correct expression should be “the cost of safe and civilized construction should be adjusted according to the actual changes in the measures, not floating”
.
During the performance of the contract project, the following statements are correct for the adjustment of contract price and construction period caused by force majeure
.
A
.
the Contractor shall bear the cost of repairing the project according to the requirements of the employer during the shutdown period; B
.
the damage to the Contractor’s construction equipment shall be borne by the employer; C
.
the damage to the permanent project shall be borne by the employer; D
.
the construction period is delayed due to force majeure and the employer requests to rush the construction, The employer and the Contractor shall bear their own casualties and property losses
.
The correct expression of option A should be “the cost of repair works by the contractor according to the employer’s requirements during the shutdown period shall be borne by the employer”
.
The correct expression of option B should be “the damage of the Contractor’s construction equipment shall be borne by the contractor”
.
7 [single choice question] due to the temporary design change of the owner, a construction project was shut down
.
The Contractor’s workers were idled for 8 working days, and the idling cost was 300 yuan / working day; The contractor rents the excavator for two shifts, the rental fee of the excavator is 1000 yuan / shift, and the power fee is 160 yuan / shift; If the Contractor’s own dump truck has two idle shifts, the depreciation cost of the truck is 400 yuan / shift, and the power cost is 200 yuan / shift, then the cost that the contractor can claim from the owner is () yuan
.
A.4800 B.5200 c.5400 d.5800 “correct answer” B “answer analysis” this question examines the composition of the claim fee
.
Labor cost: the cost of work stoppage is calculated by idling, 300 yuan × 8 = 2400 yuan
.
Equipment cost: claim for equipment cost caused by idling work
.
When the construction machinery is owned by the construction enterprise, the claim cost shall be calculated according to the machinery depreciation cost; When the construction machinery is rented from outside by the construction enterprise, the standard of claim fee is calculated according to the equipment rental fee
.
four hundred × 2+1000 × 2 = 2800 yuan
.
The total claim is 2400 + 2800 = 5200 yuan
.
8 [single choice] according to the standard construction bidding documents issued by nine ministries and commissions, the supervisor shall re inspect the concealed works
.
If the inspection proves that the project quality meets the requirements of the contract, the employer shall compensate the contractor
.
A
.
construction period and cost B
.
construction period, cost and profit C
.
cost and profit D
.
construction period and profit “correct answer” B “answer analysis” this question examines the situation that can reasonably compensate the Contractor’s claim specified in the contract terms of the standard construction bidding document
.
According to the standard construction bidding documents issued by nine ministries and commissions, the supervisor shall re inspect the concealed works
.
If the inspection proves that the project quality meets the requirements of the contract, the employer shall compensate the labor period, cost and profit of the contractor
.
For the claim caused by () and other reasons, the contractor can claim the labor cost.
.