Synchronous exercise of Chapter 3 of construction management of class II constructor in 2016

2Z103000    Construction schedule management 2z103010     Objectives and tasks of progress control of construction project( The owner     B

.

Designer   C

.

Construction party   D

.

In the process of construction schedule control, the owner’s task is to control the whole project(   A  ) The progress of the project( 2013 (a true topic)   A

.

Implementation phase B

.

strategy phase   C

.

Project life cycle   D

.

Use stage   5

.

Before controlling the overall schedule of construction project, we should first(   D    )。( (2014 real topic) A

.

carry out project structure analysis B

.

determine the work code of the project C

.

prepare the progress plan of each layer D

.

analyze and demonstrate the possibility of target implementation 4

.

The work of the demonstration of the overall progress goal of the construction project includes: ① project structure analysis; ② preparation of the progress plan of each layer; ③ structural analysis of the progress plan system; ④ project work code

.

The correct working sequence is (b)( 2013 real topic) a      B.①③④②     C.③②①④     D

.

According to the work steps of the demonstration of the overall progress goal of the construction project, the work that should be carried out immediately after the completion of the “project structure analysis” is as follows(   B   )。( 2013 (a true topic)   A

.

Investigation and data collection   B

.

Structure analysis of schedule system   C

.

Work code of the project   D

.

Prepare the progress plan of each layer   6

.

What’s right about the construction project management schedule system(   C   )。( A

.

It is composed of several independent progress plans; B

.

It is prepared by all participants of the project; C

.

its establishment is a process of gradual improvement; D

.

the progress plan system of a specific project is the only multiple-choice question; 5

.

The main contents of the general progress outline of the construction project include(   ACDE  )。 ( 2012 a real topic   Overall deployment of project implementation             B

.

  Project structure analysis    C

.

  Master schedule                     D

.

  Determine the schedule target of milestone event   E

.

  About the construction project schedule system, the correct statement is (ACDE)  )。( The project schedule system is the basis of project schedule control

.

B

.

the project schedule system should be established and improved before the implementation of the project

.

C

.

The project participants can prepare multiple different schedule systems

.

D

.

the plans in the project schedule system should pay attention to contact and coordination

.

E

.

the project schedule system can have multiple schedules in different periods

.

2 According to the function division of the plan, the construction schedule of the construction project is divided into (ACE)( Control schedule      B

.

Indicative schedule      C

.

Guiding schedule D

.

summarizing schedule      E

.

Implementation schedule 3

.

About the statement of construction project schedule control, what is correct(     ADE   )。( Each participant has the task of schedule control

.

B

.

The objectives and time scope of schedule control of each participant are the same

.

C

.

It is not allowed to adjust the schedule in the process of project implementation

.

D

.

schedule control is a dynamic management process

.

E

.

the analysis and demonstration of schedule objectives is a link of schedule control

.

In the project implementation stage, the overall schedule of the project includes(     ABDE   )( Bidding progress                              Progress of design work progress of warranty work progress of engineering construction progress of material procurement work progress 2z103020     The relationship between the construction production plan of a construction enterprise and the construction schedule of a construction project is (c)( 2013 real topic) a   Construction production plan is the collection of project construction schedule   It belongs to the same planning system, but the scope is different   They belong to two different systems, but they are closely related   There is no relationship between the two plans belonging to two different systems

.

19

.

Among the following schedules, the one belonging to the implementation construction schedule is (c)( General construction schedule of the project      B

.

Annual project construction plan C

.

monthly project construction plan        D

.

The design schedule of ten day construction production plan of an enterprise is mainly to determine the schedule of each design stage(   C     )( Professional coordination plan                  B

.

Design workload plan C

.

drawing plan                      D

.

The overall construction schedule of the design personnel allocation plan project belongs to(   D  )( The overall construction schedule of the project          B

.

guiding construction schedule of the project C

.

annual construction plan of the project        D

.

The controlling construction schedule of the project (2) multiple choice question  (   CD   )。( 2014) A

.

as the basis for the preparation of the unit’s construction schedule B

.

demonstrate the overall construction schedule C

.

determine the monthly resource demand D

.

determine the specific arrangement of construction operation E

.

determine the schedule target of milestone events 2z103030     How to make the construction schedule(   A   )。( In a network plan, the next tasks of job a are B and C, the latest start time of job B is 14, and the earliest start time is 10; The latest completion time of work C is 16 and the earliest is 14; The interval between work a and work B and work C was 5 days, and the total time difference of work a was (b)  ) God( 2012 real topic) A.3          B.7         C.8          D

.

1026

.

In a network plan, if the earliest completion time of work m is the 8th day, the latest completion time is 13 days, the duration of work is 4 days, and the minimum interval between work m and all post work is 2 days, then the free time difference of work m is (a) days( 2012 real topic) A.2         B.3         C.4        D

.

527

.

In a project network plan, the earliest completion time of work n is 17 days, and the duration is 5 days

.

There are three urgent tasks in the change work, and their earliest start time is 5 days   If the starting time is the 25th day, the 27th day and the 30th day respectively, the free time difference of working n is (d) days( 2013 real topic) a, 7      B、2      C、3      D

.

828

.

In the double code network diagram, the work is represented by (b).

.