The sun in Hainan can not be described as “hot”, but as “strong” I underestimate it when I describe it as sunny
.
If I raise my eyes, I will feel dizzy This is how the workers of Hainan refining and chemical circulating water plant evaluate and describe the scorching sun on the construction site
.
But in the scorching sun, they are full of energy, full of pride, busy figures, tough hearts, and devoted to their work
.
It seems that the weather is no longer so hot
.
01 strengthen responsibility and zero distance monitoring In order to strengthen the process supervision and overall control of the project, the party and government leaders of the construction project management department are stationed at the Hainan construction site in turn
.
During the special periods such as Spring Festival, Tomb Sweeping Day, difficult to promote the project, and critical construction, the Secretary and manager of the general Party branch arrive at the site many times to help and strictly observe the situation, actively understand the actual operation of the project, and actively help the project to coordinate the fund payment, construction and other issues Material supply, personnel deployment and other issues, to solve the actual difficulties of the project, promote the project operation
.
During the construction process, the construction scheme was further optimized
.
The underground anti-corrosion materials of 2 cooling towers 201-a and 201-b in the circulating water field, which were originally planned to be completed in 3 days, were painted in half a day, and the earthwork excavated from the nearby pipe trench was used for backfilling
.
The problem of earthwork stacking was solved, and the cost of soil transportation from 1 cooling tower in the circulating water field was saved
.
02 strengthen project management and make reasonable planning and deployment The project department, working together, refines the task objectives, compacts the responsibilities layer by layer, and strengthens the reserves of human, machine, material and other resources according to the construction progress
.
The two construction areas are divided into six construction area blocks, each of which is in the charge of an independent construction team and is equipped with independent constructors, safety officers and material officers to ensure the continuity of construction
.
In terms of safety, on the basis of full-time safety officers of the original project, the safety assistant in each construction team is strictly selected from the management personnel of the team to be responsible for the safety work in the area, and the guardian is allocated according to the construction content
.
In the aspect of progress, the project technicians strengthen the plan control work, make statistics on the daily construction progress, and subdivide it into daily according to the four level plan
.
Predict the nodes that may have plan delay in advance, and summarize in the daily production schedule meeting
.
In terms of quality, the construction personnel of regional block project shall organize the team leaders of various specialties to inspect the construction contents daily, and strictly implement the three inspection system to ensure the excellent construction quality
.
03 strengthen communication and improve work efficiency The project department actively coordinates the cooperation and cross construction of various posts, and does not need to rely on scientific management and careful construction
.
The management personnel go deep into the front line in the whole process, timely understand the difficulties and problems encountered in the construction, make efforts to ensure the continuity of each process, seize the sunny and rainy days, seize and squeeze the time to seize the operation, pour concrete at night, and construct flexibly in rainy days
.
In view of the situation that the average temperature in Hainan is too high during the day, the construction personnel will be equipped with two shifts to avoid the safety risk of high temperature and sunshine environment during the day
.
In the afternoon, the working hours will be extended to work overtime
.
In the evening, in addition to scaffolding formwork construction and other high-altitude work, reinforcement night construction, background processing and other operations will be added to play a seamless connection with the work of the next day
.
Strengthen safety production and strive for quality engineering Through strengthening the responsibility, the project department builds up the ideological defense line of safety production
.
Organize technicians to continuously optimize the construction scheme and hold technical disclosure meeting to provide strong technical guarantee for the site
.
At the same time, strictly control the quality of each link and process to effectively prevent the phenomenon of idling and rework
.
The daily inspection shall be strengthened
.
The project management personnel shall organize the construction team every day to make a pre shift call on the construction content needed on that day from the aspects of construction technology and safety hidden danger
.
The weekly inspection shall be carried out on the site quality, safety and materials under the leadership of the project manager every week
.
At the same time, the “small horn” mode is implemented for the site safety
.
Each safety officer Guardian wears a loudspeaker and plays the safety warning broadcast continuously
.
The safety broadcast is played with music, which not only plays the role of warning for the construction workers, but also relieves the work pressure and drives the workers’ enthusiasm
.
Since the commencement of the project, more than 110 safety problems have been found and investigated, and more than 20 potential safety hazards have been solved, ensuring the safe and reliable operation of the project
.
Vigorously carry out labor competition and strengthen assessment In order to carry out the labor competition of “working hard in the second quarter, achieving double over half, and presenting excellent achievements to the 100th anniversary of the founding of the Communist Party of China”, we signed the labor competition book with the construction team, and according to the content of the labor competition book, we used the integral system to conduct labor evaluation every week and every month according to the construction node, plan, acceptance rate, safe and civilized construction, and regularly fulfilled the competition rewards and punishments, It creates a good atmosphere for all the staff participating in the construction to strive for advancement and be a pacesetter, and promotes the smooth progress of project construction and production
.
In the labor competition activities, the project department scientifically decomposes the objectives and tasks, holds daily production progress docking meeting every Tuesday at 5:30 p.m., and strengthens the construction organization
.
On the basis of the original site construction personnel, more than 100 new construction personnel are deployed to step up the construction
.
Communicate with material suppliers in advance to ensure the supply of construction materials in place
.
The construction safety and quality shall be strictly monitored, and the construction progress shall be synchronized with the labor competition plan
.
In April, a total of 9789 cubic meters of concrete were poured and 1264 tons of steel bars were bound
.
At present, all the staff of the project department are full of enthusiasm, confidence, anchor the goal, go all out, work hard, continue to carry forward the spirit of “not delay a day, not slack a day”, overcome the scorching sun, race against time, forge ahead to the goal, and promote the realization of the goal of presenting a gift to the 100th anniversary of the founding of the party with outstanding achievements in hard work..
.