According to the Jingmen daily news on the 6th, the Jingmen Railway Office learned that the announcement of total price contract bidding for the construction of Jingmen Jingzhou railway project has been issued
.
The three bidding sections are planned to start at the end of June, with a construction period of three and a half years
.
According to the person in charge of Jingmen railway office, the new main line of Jingmen Jingzhou railway is 77.479km long, with a total operating mileage of 78.537km One intermediate station (Shayang west station)
.
The xiankai section (19.58km) in Shayang County, which started construction last year, can be regarded as bid section II
.
The specific conditions of the three bidding sections are as follows: bid section 1: left dik002 + 402.645 of Jingmen super large bridge on Jingmen Railway (excluding 20 piers on the left track) and right yd1k002 + 366.635 of Jingmen super large bridge on Jingmen Railway (including 13 piers on the right track) – dk20 + 325; The length of main line is 24.523km; It includes pre station project and post station interface project, ballastless track bed construction, box girder prefabrication and erection
.
The estimated contract price is 2 billion yuan
.
The route mileage of bid section III is dk39 + 904.695 ~ dk58 + 836, with a total length of 18.931km, including pre station works and post station interface works, ballastless track bed construction, box girder prefabrication and erection
.
The estimated contract price is 1.5 billion yuan
.
The route mileage of bid section 4 is dk58 + 836 ~ dk70 + 947.737, with a total length of 12.199km, including Jingzhou station reconstruction project, front station project and rear station interface project, ballasted track bed construction, box girder prefabrication and erection, double block sleeper prefabrication project of the whole line, prefabrication and transportation of small prefabricated components of the whole line, track laying project of the whole line The integrated design project of the interface between the station building and the front part of the station and the reconstruction project after the station in the station reconstruction project
.
The estimated contract price is 1.8 billion yuan
.
At this point, all four sections of the Jingmen Jingmen railway will enter the construction stage! The official account of WeChat daily in Hubei daily exceeded 2 million, we sent benefits
.
We have carefully prepared a number of notebooks of Hubei Daily as prizes for readers
.
The way to get benefits is very simple
.
As long as you leave a message for any manuscript we push every day, the top two readers in the ranking of comments and likes in a manuscript (the number of likes should be more than 30), you can get the notebook of Hubei Daily with high face value (as shown in the figure below)
.
The rules of award: 1
.
the winner should also pay attention to the WeChat official account of “Hubei daily”
.
The number of likes in the message is more than 30 before 9:00 the next day; The top two comments are like
.
2
.
As of 9:00 a.m
.
the next day, Xiaobian will reply you the specific way to receive the prize
.
3
.
Each person is limited to one book
.
The number is limited
.
Please join us.
.