Policy interpretation of “Chengdu construction site management regulations”

01 legal basis  《 Construction law, Sichuan construction management regulations, etc                ( 1) Scope of application:             In the city’s construction site construction activities in the implementation of supervision and management( These Regulations are not applicable to emergency needs such as rescue, decoration of residents and transportation of construction waste)

.

                         ( 2) Division of responsibilities:             The municipal housing and construction department is responsible for the supervision and management of the construction site of the city

.

The district (city) and county housing construction departments are responsible for the supervision and management of the construction site within their jurisdiction, and accept the business guidance of the municipal departments

.

The departments of urban administration and ecological environment shall supervise and manage in accordance with their respective responsibilities

.

                         ( 3) Management content:             The comprehensive evaluation of construction organization, quality, safety and green building shall be carried out

.

The comprehensive evaluation results shall be included in the credit evaluation system of the main body of the construction market, and shall be published regularly as one of the conditions and basis for revoking and upgrading the qualification

.

                         ( 4) Construction management:             In case of general contracting, the general contractor shall be responsible for the unified management of the construction site, and the subcontractor shall be responsible for the management within the scope of subcontracting; Professional projects directly contracted out by construction units shall be subject to on-site management by general contractors, and unified management agreements shall be signed between construction units, professional contractors and general contractors

.

1

.

The construction unit shall fulfill its responsibilities: establishing a construction management organization; Formulate management system and assessment methods; Clarify the responsibilities of the general contractor and subcontractor, and sign the safety production agreement; Organize relevant units to carry out construction inspection regularly to eliminate hidden dangers;   Take overall responsibility for dust control and bear the cost of civilized construction

.

  Violation of this article shall be dealt with in accordance with the provisions of Article 42 and the laws and regulations on the quality of construction projects

.

2

.

The construction unit shall fulfill its responsibilities: setting up management organization and providing full-time quality and safety management personnel; Carry out construction according to quality and safety operation regulations and standards, construction scheme and design requirements; Implement and implement various systems and measures such as construction site quality; The cost of safe and civilized construction shall be properly invested and used and shall not be misappropriated

.

  Violation of this article shall be dealt with in accordance with Article 42 and laws and regulations on construction project quality

.

  3

.

Other requirements of the construction unit: prepare the construction organization design according to the scale and characteristics of the project

.

A special construction scheme shall be prepared for divisional and subdivisional works with high risk (foundation pit support, dewatering, earth excavation, formwork engineering and support system, lifting, installation and disassembly, scaffold, curtain wall installation, manual hole digging pile, etc.), which shall be reviewed and signed by the technical director of the construction unit, the chief supervision engineer of the project and the project director of the construction unit, Only then can it be implemented

.

Violation of this article, according to the first paragraph of Article 43, shall be ordered to make corrections within a time limit and imposed a fine of 10000-30000 yuan

.

  4

.

The supervision unit shall fulfill its responsibilities: implement supervision and bear supervision responsibilities

.

For divisional and subdivisional works with high risk, the director shall confirm the quality and safety status of each construction procedure before instructing the construction unit to proceed to the next construction procedure

.

In case of violation of this article, he shall be ordered to make corrections within a time limit and be fined 10000-30000 yuan according to the first paragraph of Article 43

.

5

.

The five main bodies should strengthen the quality and safety management: the building materials and equipment should meet the quality standards of the national industry, advocate the use of green building, implement the green building standards, promote the modernization of construction technology, and incorporate them into the construction conditions; For the safety inspection and inspection of the construction site, the hidden dangers of safety accidents should be eliminated in time, and the behaviors violating the construction safety standards or operation should be stopped immediately; Violation of this article shall be dealt with in accordance with the first paragraph of Article 42 and other laws and regulations on construction project quality

.

  The construction unit shall go through safety supervision procedures

.

Command and operation against regulations are prohibited

.

Violation of this article, according to the first paragraph of Article 43, shall be ordered to make corrections within a time limit and imposed a fine of 10000-30000 yuan

.

In case of any safety accident or public health emergency, the person in charge of the construction or construction unit shall promptly take measures and immediately report to the construction department and relevant departments

.

Violation of this article shall be dealt with in accordance with the first paragraph of Article 42 and other laws and regulations on construction project quality

.

   6

.

Suspension of Construction: the construction unit shall report to the construction license issuing authority

.

During the shutdown period, the construction unit shall keep the enclosure and entrances and exits of the construction site clean and tidy

.

In case of violation of this article, the construction unit shall be ordered to make corrections within a time limit according to the second paragraph of Article 43; Those who fail to make corrections within the time limit shall be fined 20000-50000 yuan

.

7

.

Civilized construction of construction unit: (1) complete the construction of civilized construction facilities before commencement, and sign the letter of commitment for civilized construction with housing construction department( 2) Implement closed management, and set up continuous closed enclosure or enclosure (hard material, clean surface, enclosure height no less than 2 meters, the construction enclosure of traffic intersection shall be more than 1.2 meters away from the ground to keep transparent), in violation of this article, according to the first paragraph of Article 45, order to correct and impose a fine of 20000-100000 yuan

.

Those who refuse to correct shall be ordered to stop work for rectification( 3) If a construction notice board is set up at the eye-catching position of the entrance and exit, in violation of this article, it shall be ordered to make corrections within a time limit according to the second paragraph of Article 43; Those who fail to make corrections within the time limit shall be fined 20000-50000 yuan( 4) The construction unit shall harden the site entrances and exits and main roads and keep them unblocked

.

In case of violation of this article, the construction unit shall be ordered to make corrections and be fined 20000-100000 yuan according to the first paragraph of Article 45; Those who refuse to make corrections shall be ordered to stop work for rectification( 5) The external protective frame of construction shall be sealed with dense mesh protective net or other protective facilities with flame retardant function, and the sealing shall be higher than the working face and carried out synchronously

.

The protective net shall be kept clean, firm and free from damage

.

In case of violation of this article, it shall be ordered to make corrections within a time limit in accordance with the second paragraph of Article 43; Those who fail to make corrections within the time limit shall be fined 20000-50000 yuan

.

8

.

Fire management: the construction unit should strengthen the fire safety management and implement the responsibility system of fire safety management

.

The construction and supervision units shall strengthen inspection, supervision and other fire control work

.

Any violation of this article shall be dealt with by the fire rescue agency in accordance with the fire management laws and regulations in accordance with the second paragraph of Article 42

.

                ( 5) Construction site pollution prevention and control:             1

.

Prevention and control of noise pollution: (1) the construction unit shall set the operation equipment which is easy to produce noise at the side far away from houses, hospitals and other noise sensitive buildings

.

In case of loading and unloading construction materials, the operation mode of reducing noise shall be adopted

.

In case of violation of this article, it shall be ordered to make corrections within a time limit in accordance with the second paragraph of Article 43; Those who fail to make corrections within the time limit shall be fined 20000-50000 yuan( 2) Construction at night (from 22:00 p.m

.

to 6:00 a.m.) is prohibited during the middle school entrance examination and college entrance examination; On the day of the examination, it is forbidden to engage in noise pollution construction activities around the examination room

.

  In case of violation of this article, the construction activities shall be ordered to stop and a fine of 2-5 yuan shall be imposed according to the first paragraph of Article 44; Those who refuse to make corrections shall be ordered to stop construction and fined 100000-200000 yuan( 3) Construction at night is prohibited without approval, and continuous construction is required due to production process requirements; Urban roads need to be occupied or excavated for the construction, reconstruction or expansion of municipal infrastructure such as urban roads; If it is really necessary to carry out construction within the scope of the Third Ring Road (such as excavation of foundation pit, etc.) and apply for “night construction permit”, in violation of this article, according to the second paragraph of Article 44, unauthorized night construction shall be ordered to correct and fined 10000-30000; Those who refuse to make corrections shall be ordered to stop construction and fined 50000-100000 yuan

.

2

.

Dust pollution prevention and control: (1) construction unit: the cost of dust pollution shall be included in the project cost, and the responsibility of dust pollution prevention and control of construction unit shall be specified in the contract.

.