However, the Dongguan bridge has not been fully completed yet.
According to the relevant provisions of the road traffic safety law of the people’s Republic of China, it is hereby announced as follows: 1.
The passage is temporarily adjusted, and passing vehicles need to pass according to the instructions of traffic signs.
2、 Closure construction date: August 20 to September 10, 2021 (Hebin Road intersection) September 11 to September 30, 2021 (Hebin East Road intersection).
The intersection of Hebin road and Dongguan bridge in Fushan District has been fully closed for 20 days since the early morning of September 11.
Please slow down and drive carefully! At the same time, remind everyone that the intersection of Hebin East Road and Dongguan bridge will be fully closed from the early morning of September 11.
Yantai Fushan District Housing and Urban Rural Development Bureau on September 9, 2021 from: urban drainage service center of Yantai Urban Management Bureau, traffic police brigade of Fushan branch of Yantai Public Security Bureau, housing and Urban Rural Development Bureau of Fushan District, Yantai The copyright of this article belongs to the original author.
Please understand and support the inconvenience caused.
Start construction tomorrow! Take a detour! ↑ ↑ ↑ ↑ ↑ ↑ ↑ drainage reconstruction construction of Yinhai Road, Laishan district on September 11 Road traffic adjustment due to drainage reconstruction construction, From September 11, 2021 to September 13, 2021, the intersection of Guanhai road and Yinhai road in Laishan district faces west, and the north side of Yinhai road is about 40m away from the middle of Guanhai road.
During the construction period, passing vehicles and pedestrians are invited to bypass according to the on-site warning and prompt signs.
The intersection of Hebin road and Dongguan bridge, which is planned to be lifted on September 10, has been completed and can pass normally since the early morning of September 11.
If there is any infringement, please contact us..
Closed area: all lanes at the intersection of Dongguan bridge and Hebin road and the intersection of Dongguan bridge and Hebin East Road.
3、 Specific closure type: totally closed, no passage.
According to the construction needs of Dongguan Bridge Road project, traffic control shall be implemented at the intersection of Dongguan bridge and Hebin road and the intersection of Dongguan bridge and Hebin East Road.
The construction unit will also increase human and mechanical investment to quickly promote the construction progress.