Construction log of Jiemei Project Department of Wuxi Jingteng Building Decoration Engineering Co., Ltd. 20210920

Pre shift Education: woodworking, hydropower, air conditioning handling..

Mobilization record of materials, components and accessories: there is no material mobilization coordination today: there is no coordination temporarily.

Production records: carpentry: 11 people, ceiling construction on the first floor, ceiling fabrication in the elevator hall on the second floor, light steel keel partition wall sealing plate on the third floor, light steel keel partition wall fabrication on the sixth floor, wall sealing plate bricklayer on the seventh floor: 3 people, wall painting of East and West toilets on the third floor, water electrician: 7 people, transformation of fire pipes and fire boxes, installation of electrician sleeves, production and installation of sewer pipes in toilets, Fabrication of strong current bridge weak current: 2 persons, installation of weak current bridge on the fourth floor, installation of weak current bushing, air conditioning team: 6 persons, installation and handling of air conditioning equipment on the seventh floor: 5 persons, cleaning construction progress of each floor: first floor: 35% of suspended ceiling, 50% of column wrapping, second floor: 50% of light steel keel partition wall sealing plate and 70% of toilet wall painting, 20% of the ceiling of the elevator hall has been fabricated on the third floor: the wall of the toilet has been painted on the fourth floor: the installation of weak current bridge has been completed 70% on the fifth floor: the installation of wall keel has been completed 95% on the sixth floor: the installation of weak current bridge has been completed 40% on the seventh floor: the wall sealing plate has been completed 50%, the installation of electrical sleeve on the top has been completed 90%, and the installation of strong current bridge has been completed 50% of the technical quality and safety work records: safety and technical disclosure of each team every day, Confirm the construction scope and relevant safety precautions on that day, conduct safe and civilized construction and ensure the project quality.

Cuplock System Scaffolding