At Jinhai intersection of Yanggao Middle Road, management measures are taken to prohibit north-east and south-west left turns.
Non motor vehicles get off at the intersection, and pedestrian and non motor vehicle waiting areas are set at the intersection* Focus 4 of figure source: Shanghai traffic police micro released highway S3 (Lianggang Avenue Interchange of zhoudeng highway – g1503 highway) and highway S3 (Lianggang Avenue Interchange of zhoudeng highway – g1503 highway) as the “one ring and twelve radiation” radial highway of the municipal expressway network, which is the connecting channel between the central urban area and Pudong New Area, Lingang New City and Fengxian District* Location relationship between new ramps of s3-g1503 hub interchange and existing ramps of toll station according to the project progress, s3-g1503 hub interchange is planned to be implemented in the near future.
Passing vehicles need to be diverted to Yanggao Middle School Road (central interchange Jinhai Road) and Yanggao Middle School Road (central interchange Jinhai Road) rapid reconstruction project, starting from central interchange (West of Pingdu Road) in the west, Jingang Road (excluding the intersection of Jingang Road) in the East and Jiaodong Road (including the intersection of Jiaodong Road) in the north* According to the plan, some ramps of Jinhai Road Interchange on Yanggao middle road need to be demolished and rebuilt.
First, small partners with travel plans on holidays must pay attention to driving safety-.
The project is planned to start at night on September 18, 2021 (today), and is expected to be completed on March 20, 2022, with a total construction period of about 6 months* Focus 4 of figure source: Shanghai traffic police micro released that during the construction period, the existing overpass bridge of Yanggao middle road and Jinhai Road will be closed, and motor vehicles will be diverted to the new access road on the ground to ensure that the number of lanes in all directions is consistent with the original overpass bridge.
Schematic diagram of detour route of some roads * Linhai highway toll station Fengcheng town bypass * wahong highway toll station Qingcun town bypass route thousands of roads are safe.
After completion, S3 highway is connected with g1503 expressway through ramps to form an interchange.
My friends who plan to travel by car in the city during the holiday have noticed that there are two more interchanges in Shanghai.
Because some main lines and new ramps of S3 highway are above the ramps of existing Fengcheng toll station of g1503 highway (location overlap), the original ramps need to be removed and rebuilt, and g1503 Fengcheng toll station needs to be closed during construction.
The project is planned to start at night on September 17, 2021 (yesterday) and complete by the end of December 2022, with a total construction period of about 15 months.
The interchange project of s3-g1503 hub mainly includes 1 main line overpass, 8 ramps and subgrade widening with the current main line of g1503.