Weekly report on demolition and construction of indoor reclaimed water system in Xinghong Yayuan (August 28, 2021 to September 3, 2021)

Next week’s plan: 85% of the holes are blocked, the wall base treatment is completed, and 30% of the slope making layer is completed…

Last week’s plan:   The installation of branch and riser is completed, 40% of the hole is blocked, and 30% of the wall base treatment is completed.

Lifting Pin Anchor

The completion of this week:   The installation of branch and riser is completed, 40% of the hole is blocked, and 30% of the wall base treatment is completed.