Construction of secondary piping without slotting 210930

After the distribution box is fixed, complete the piping and hand over to the civil masonry.

Using this process, the secondary piping is formed at one time, reducing the slotting waste cleaning and other processes, and the on-site physical quality is also improved, but at the same time, there are some construction difficulties.

This method is worthy of your reference and implementation! Temporary support frame of distribution box auxiliary secondary piping slotting free construction step 1 processing and prefabrication of temporary support frame of distribution box process and prefabricate temporary support frame according to the model of distribution box, in which the function of retractable regulator is to adjust the elevation of distribution box and fix it.

U Bar Anchor

Step 4 after the piping is completed, hand over to the civil masonry.

Step 3 the distribution box shell is fixed on the support frame, and the angle steel is erected in the box body by using the reverse port of the box to effectively erect and fix the box cantilever on the support frame.

The construction technology of secondary piping without slotting came into being.

Masonry slotting not only destroys the stability of secondary structure, but also prone to common quality problems such as cracking.

In this regard, the installation branch of China Construction * Bureau * company applies innovative technology in the project and adopts the temporary support frame of distribution box to assist the secondary piping slotting free construction, which not only increases the construction convenience, but also further improves the construction quality.

Step 2 accurate positioning, erection and setting out of the electric box support frame to ensure accurate control of the embedded depth of the box into the wall.

The construction of secondary piping without slotting adopts traditional construction technology.

On site completion effect..