The most easily omitted visa items on the construction site, Party A does not want to give!

In case of rock, the depth into the rock should be signed in time

.

When the site is narrow or the slope is not stable enough to pile up enough backfill soil on site, the outward earthwork volume and distance should be signed

.

The construction unit shall be responsible for the three supplies and one leveling of the site

.

” It’s free

.

During the foundation construction period, if the construction period is delayed due to rain or due to Party A’s reasons, the cost of drainage and precipitation can be approved by the team

.

Of course, if the construction is stopped for a long time, it is necessary to record the period of suspension

.

The price of digging wet soil is higher than that of dry soil, and the price of digging silt is higher

.

The scene of the crime is located in xiameiqiao street, Beihu district

.

We can only call them” instruments

.

The accident happened in a newly developed area, and there were not many pedestrians and vehicles passing by

.

No matter how poor you are, no matter how rich you are

.

It’s natural to see if the earthwork transportation distance is favorable

.

It is also the principle of long-term visa to remember not to wait until the construction starts, at least once a month

.

He went to the car and found that Zhou Wanming was still in the car, “bleeding a lot.”

.

If Party B also participates in the work, it can negotiate with Party A

.

[earthwork part] underground water is not considered in the bidding of earthwork

.

If the excavated soil is transported away and backfilled and then backfilled, the cost will not be calculated unless it is clearly signed

.

According to Chen Ming, Zhou Wanming was injured in the head

.

Because in the bidding, most of the soil is piled up on site, and the surplus soil is transported out

.

If it doesn’t exceed the scope of the list, you have to sign the transportation distance

.

If seepage is found in the excavation, the height of underground water level can be signed

.

If there are underground obstacles, the visa should be signed, and the cost of clearing underground obstacles is not cheap

.

A homicide happened in Beihu District of Chenzhou City, 100 kilometers away

.

Otherwise, the time is too long, the supervisor of Party A can not assess, and it will be very troublesome to make up the signature later

.

“Those injured with instruments,” Chen Ming said, “the specific identification has not yet come out

.

It was Yan Changyong who committed suicide two hours ago

.

Zhou Wanming, a 58 year old construction owner, was killed in Sima Road, about 50 meters away from the second phase project of Taoyuan community in Fucheng

.

In the foundation construction, the brick formwork is used in response to Party A’s requirements to rush the schedule or consider the slope instability and need to be backfilled as soon as possible

.

In addition, if the water seepage is large, the construction scheme can be prepared to apply for drainage and dewatering measures and slope support measures

.

If there is no requirement in the bidding, it can also be signed, and the price of brick formwork is higher than that of formwork

.

We all know that the oil price is so expensive now

.

The hidden records should be as detailed as possible, that is to say, at least: hole depth, pile length, reinforcement cage length, void length, pile diameter and rock depth

.

[pile foundation part] in addition to making records of concealed works, the pile foundation should also pay attention to the certification of underground obstacles

.

On November 19, Chen Ming, a policeman from the Criminal Investigation Brigade of Beihu branch of Chenzhou Public Security Bureau, told the surging news that on the morning of the crime, Zhou Wanming’s son-in-law Li walked out of the construction site and saw his father-in-law’s car parked on the roadside, but the door was not closed

.