Can you really write construction log and Safety log? Let’s look at the standard writing

The start and end time of water and power cut must be recorded clearly, what work is being carried out during water and power cut, and whether losses are caused.

Welding records shall also be recorded in detail, including welding position, welding method (arc welding, electroslag pressure welding, overlapping double-sided welding, overlapping single-sided welding, etc.), welding current, welding rod (flux) brand and specification, welding personnel, welding quantity, inspection results, inspectors, etc.

Today is the day of June, but the filling of the Construction Safety log often stays in the middle of May, and even in March and April..

3.

2、 Work content: 1.

2.

5、 Other contents: 1.

5.

Attendance must be recorded by division of labor, and the total number of workers shall be recorded.

Understanding of Safety log construction safety log is a continuous and detailed record of important production and technical activities in the whole construction process by full-time safety officers from the beginning to the completion of the project.

(5) As the construction data kept by the construction enterprise, the information recorded in the Construction Safety log that cannot be revealed in other engineering documents for various reasons may become the basis for judging the truth in the future.

2.

Construction position.

It mainly records the illegal operation, illegal command, safety problems and hidden dangers that have occurred on the construction site, and deals with the problems found.

5.

Whether the construction is normal; 5.

Arrival and operation of personnel, materials and machinery; 3.

The names, axes and floors of divisional and subdivisional works shall be clearly written at the construction site.

Timely, truthful and detailed records shall be made.

3、 Inspection contents: 1.

Whether there is accidental shutdown; Whether there are quality problems; 7.

Only when we have an accurate understanding of the Construction Safety log, can we accurately grasp the compilation idea of the Construction Safety log.

3.

1、 Basic contents: 1.

Date, weather, temperature, project name, construction position, construction content and main process applied; 2.

Mobilization and inspection of materials.

1.

The original meaning of “Zhi” refers to the written records.

In the past, it was not difficult to find the Construction Safety log of some projects.

Source: the network copyright belongs to the original author.

Construction machinery failure and treatment.

6.

4、 Inspection contents: 1.

Filling contents of Safety log 1.

4.

Quality inspection: quality inspection and treatment records of concrete pouring and forming, reinforcement installation and welding, brick masonry, formwork installation and removal, plastering, roof engineering, floor engineering and decoration engineering on that day; Concrete curing records, mixing amount of mortar and concrete admixture; Causes and treatment methods of quality accidents, and effect verification after quality accident treatment.

Daily recording shall not be interrupted.

The construction diary shall be recorded by the foreman of Building No.

The orientation of Construction Safety log in understanding should be: (1) Construction Safety log is a record.

Inspection opinions and decisions of relevant leaders, competent departments or various inspection teams on project construction technology, quality and safety.

Second, the contents to be recorded in the construction log shall be clear.

The contents of the construction log can be divided into five categories: basic contents, work contents, inspection contents, inspection contents and other contents.

The main construction contents of the day must correspond to the construction parts.

2.

It records the daily events related to construction safety in the construction process.

3、 There are major problems in the filling process (1) failing to fill in on time and making materials for inspection:   What happened on that day was not recorded in the log of that day, and there was a phenomenon of post compensation.

4.

3.

Writing construction log and Safety log is one of the two basic tasks that construction workers often contact.

The test block name, floor, axis and number of test block groups shall be indicated.

6.

(3) The Construction Safety log is the notepad of the project and the most detailed first-hand data reflecting the construction safety production process.

Construction preparation and implementation of measures in winter and rainy season.

Maintenance records shall be detailed, including maintenance parts, maintenance methods, maintenance times, maintenance personnel, maintenance results, etc.

2.

It can accurately, truly and subtly reflect the construction safety situation.

(1) The basic content includes the filling in of date, week and weather; (2) The construction content includes the name of the sub item, the location of the layer, the working team, the number of workers and the progress of the construction; (3) The main notes include: ① patrol inspection (discovery of potential safety accidents, illegal command, illegal operation, etc.); ② Mobilization records of facilities and supplies (quantity, place of origin, label, brand, number of certificates, etc.); ③ Facility acceptance; ④ Equipment and facilities, construction electricity, “three treasures and four openings” protection ⑤ illegal operation, causes, treatment opinions and treatment methods of potential accidents (or near misses); ⑥ Other special circumstances.

In order to meet the inspection of the company or other superior departments, they shut themselves in the office and write “memoirs”.

2.

Date, week, weather and average temperature.

Construction safety; 8.

Design change, technical approval notice and implementation.

3.

In case of personnel change during the process, handover procedures shall be handled to maintain the continuity and integrity of the construction diary.

3.

3.

4.

Recording personnel usually do not fill in the Safety log in time.

(4) The Construction Safety log can serve as a document interface and can be used to trace things that are not in other documents.

The Construction Safety log is a material formed by daily written records from commencement to completion.

(2) The Construction Safety log is an evidence.

It is the proof of whether the equipment and facilities have been accepted and whether the safety and quality personnel have inspected the potential safety hazards on site.

1.

Recording time: from commencement to completion acceptance.

Third, pay attention to some details in the filling process.

The inspection records are very detailed and can also replace the construction records.

2、 The contents of the construction safety diary can be divided into three aspects: basic contents, construction contents and main notes.

4.

Whether there is any superior or supervisor’s instruction and rectification.

The seemingly simple work has an investigation on the sense of responsibility and specialty of construction workers.

It is not only a true portrayal of the daily safe construction of the project, but also the basis for the cause analysis of engineering construction safety accidents.

Fabrication of test block.

Material consumption records and construction progress records; 4.

The construction log shall be filled in according to the unit project.

3.

Main contents of relevant meetings on the construction site.

The recorder shall sign and the leader in charge shall read and sign regularly.

Elephant Foot Ferrule

The presence of the supervisor and the certification and signature of the project; 9.

Safety inspection and treatment (correction) of potential safety hazards.

The concealed contents, floors, axes, subdivisional works, acceptance personnel, acceptance conclusions, etc.

Power, water and shutdown.

Acceptance of concealed works.

The average temperature can be recorded as XX ℃ – XX ℃, and the weather is recorded in the morning and afternoon respectively.

The batch number, quantity, manufacturer and acceptance of incoming materials shall be indicated, and the inspection results after submission for inspection shall be supplemented later.

Technical and quality requirements, opinions and implementation of the construction unit and the supervision unit for the project construction.

How to record the construction log? First, understand the requirements for filling in the construction log.

Promotion and use of special measures, construction methods, new technologies and new materials involved in construction.

When writing, the handwriting must be neat and clear, and it is best to write in imitation Song typeface or regular script.

2.

Attendance and operation director.

How to stand out in construction log and Safety log? Look at the following experience! Main contents of the construction log 1.

shall be indicated.

The construction safety diary has a very important position in the whole project archives.

Other inspections, such as civilized construction and site appearance management.

Construction task disclosure, technical disclosure and safety technical disclosure.

2.

Other inspection records must be specific and detailed, not general.

Construction content and actual completion of the day.

External environment and geological changes; 6.