Construction progress: Dongling road Xinning Street: ① The civilized construction team shall scrub the enclosure and clean the site.
Enclosure pile construction team: 6 operators.
On November 12, 2021, the eighth day of October of the lunar calendar, the weather is fine, the temperature is 2 / – 10 ℃, and the south wind is level 1.
③ Reinforcement cage processing.
(4 operators) ② Three bored cast-in-place piles (b-216, b-149, b-145) were completed today, with a total of 122 completed and 356 remaining.
(7 operators) ④ The temporary construction team constructs the material shed of the reinforcement processing yard in the west of Nissan.
On site mechanical equipment: 2 rotary drilling rigs, 1 cage roller, 2 hook machines and 4 cranes…
(6 operators) ③ Reinforcement cage processing.
② Clean the site for civilized construction.
Machinery and personnel allocation: Temporary construction and civilized construction team: 12 operators.
Reinforcement cage processing team: 7 operators.
(8 operators) operation scenario: ① Drilling construction of bored cast-in-place pile (b-145).