Ministry of housing and urban rural development’s comments on code for valuation of bill of quantities of construction projects (GB 50500-2013) was revised to form the valuation standard of bill of quantities of construction projects (Exposure Draft), The relevant provisions on safe and civilized construction cost are as follows: ten point two Safe and civilized construction cost 10.2.1 the content and scope of use of safe and civilized construction cost shall comply with the provisions of relevant documents and engineering quantity calculation standards of national, provincial and industrial construction competent departments.
10.2.2 The employer shall prepay 50% of the total cost of safe and civilized construction to the Contractor within 28 days after commencement, and the rest shall be decomposed according to the principle of arrangement in advance and paid at the same time as the project progress payment.
Otherwise, the employer has the right to order it to make corrections within a time limit; If it fails to make corrections within the time limit, it may be ordered to suspend the construction, and the increased expenses and / or delayed construction period shall be borne by the contractor.
In the 2013 edition of code for valuation with bill of quantities of construction projects, the relevant provisions on safe and civilized construction cost are that the employer shall prepay not less than 50% of the total safe and civilized construction cost of the current year within 28 days after the commencement of the project, and the rest shall be paid at the same time as the progress payment…
Fixing Socket Angular End Nail Plate
10.2.4 the Contractor shall make a special fund for the safe and civilized construction cost, which shall be separately listed in the financial accounts for future reference and shall not be used for other purposes.
10.2.3 if the employer fails to pay the safe and civilized construction fee on time, the contractor may urge the employer to pay; If the employer fails to pay within 7 days after the expiration of the payment period, the contractor has the right to suspend the construction, and the employer shall be liable for breach of contract.