Construction organization of battery production project-51-steel structure installation

All components of the project are hoisted by the comprehensive hoisting method in the span, that is, the crawler crane is used to hoist the columns, beams, longitudinal supports and other components between the spans in order to form a stable system, and then hoist the next span.

Lighter materials / components can be handled on site manually.

4.5.2 selection of construction machinery four 30 ton crawler cranes are selected for the main power house.

Single machine rotation method is adopted for steel column hoisting.

Erection Anchor

Solar power stations, solar water heaters, electric vehicles and energy storage power stations are all based on mass production of batteries, and solar cell production is the demand side of purification projects.

The hoisting process is: steel column → support between columns → roof truss → roof support system (including skylight) → roof slab.

The steel structure shall be hoisted by comprehensive hoisting method, that is, after installing a row of transverse steel columns, the corresponding steel beams and support system shall be installed immediately to form a stable system.

Thank # Wenmeng for pursuing excellence, Zhai Lijuan   Shared material.

The East and west wall panel systems shall be carried out after the installation of the main body of the steel structure, and the north and south wall panel systems shall be carried out after the structural capping of the office area and equipment room.

You can enter if you abide by the rules  》 (open the link to view the details.)     For more purification materials, please refer to 20210927 for more than 60 purification materials and 9.9 for 30 purification materials  、 “Video, audio, articles, all the purification you want is here”   Whether it is “like the author” or forwarding, or even opening the ads automatically added in and after the text, it can add a “Shandong big steamed bread”! ********************************************************************..

   4.5 steel structure installation 4.5.1 installation principle according to the characteristics of the project, the installation principle is: first the main body, then the enclosure, first the lower part, then the upper part.

This device has applied for national patent.

Therefore, from today on, we will share the construction organization design of solar cell production projects.

4.5.3 the steel structure column can be installed after the bearing platform concrete is cured to 75% of a certain strength.

The steel beam and support system shall be installed alternately with the steel column, and the installation sequence is the same as that of the steel column.

We adopt the “new technology of roof slab high-altitude moving and pressing construction”, and use profiler, tower, winch, walking controller and other tools to assemble track walking high-altitude pressing plate device on the roof of the attached rooms on both sides of the plant.

  More contents: 1 – project overview 2 – wastewater treatment station 3 – bulk gas station 4 – construction objectives 5 – high altitude operation 6 – overall arrangement of project implementation 7 – arrangement of construction team 8 – main construction stage 9 – construction method of divisional and subdivisional works 10 – elevation measurement control 11 – settlement observation 12 – installation of embedded anchor bolts 13 – Determination of bolt position 14 – formwork removal Concrete curing 15 – Super leveling professional construction 16 – floor construction process 17 – cover and protect with film 18 – formwork installation 19 – concrete pouring 20 – concrete surface treatment 21 – steel structure fabrication 22 – detail design 23 – connection node design 24 – steel structure fabrication process 25 – steel structure processing and fabrication process 26 – setting out Allowable deviation of template 27 allowable deviation of steel after correction 28 cutting 29 allowable deviation of sawing 30 allowable deviation of refined bolt hole 32 allowable deviation of bolt hole spacing 33 assembly principle 34 principle of steel plate splicing 35 allowable deviation of welding structure assembly 36 H-section steel assembly 37 welding H-section steel column fabrication 38 welding process flow chart of steel structure 40 welding rod Table 41 – General Provisions for welding flux selection 42 – automatic submerged arc welding 43 – CO2 gas shielded welding 44 – carbon arc gouging 45 – welding sequence 46 – member derusting method and inspection standard 47 – steel member coating method 48 – derusting and repair of coating defects 49 – Parts prohibited from painting 50 – finished product protection and transportation 51 – steel structure installation   Recognize and implement the group rules, and welcome the purification of four groups.

The owner requires that the roof slab is a single slope, a whole slab, without overlapping and on-site processing.