It will form a cross sea and cross river channel group in Dawan district together with Hong Kong Zhuhai Macao Bridge, Shenzhen China channel, Nansha bridge and Humen Bridge, help build a modern comprehensive transportation system and promote one hour access between major cities in Guangdong, Hong Kong and Macao.
The span of Huangmaohai bridge is 720 meters.
Figure / Guangdong satellite TV ▲ effect drawing of Huangmao sea cross sea channel after its completion, Huangmao sea channel will become an important channel connecting western Guangdong.
It is expected that the two main bridges will fully enter the tower column construction stage before the Spring Festival.
△ the beam of the first section was erected and closed successfully.
The Huangmaohai sea crossing channel is expected to be completed and opened to traffic in 2024.
△ introduction to the middle tower and West Tower bearing platform project of Huangmaohai bridge under construction Huangmaohai sea crossing channel project connects Zhuhai and Jiangmen Taishan.
The reinforcement binding of the second layer bearing platform of the East Tower of Gaolan Port Bridge is under way, and the concrete pouring of the bearing platform of the west tower has been completed; The tower base pouring of the East Tower of Huangmaohai bridge has been completed, the third section of the middle tower is under construction, and the west tower has been constructed to the fourth section of the tower.
The beam of the first section is 16.5m wide, 3.8m long and weighs 114 tons.
The total length of the project is about 31 km, including about 14 km of sea crossing section.
New news of Huangmao sea cross sea channel! On December 24, Guangdong Communications Group announced that the first segment beam of Huangmaohai sea crossing channel project was successfully erected on December 23, opening the prelude to the superstructure construction of Huangmaohai project.
The design standard of two-way six lane is adopted, with 2 super large cable-stayed bridges, 1 medium and long tunnel and 4 interchanges.
Look forward to it! For more authoritative information, please pay attention to ↓ article / Zhuhai release, correspondent Chen Ying, Yue Lujian map / Zhuhai release, responsible editor Li Jianshu, editor LAN Huilong, editor Jiang Chuanxi..
Ringlock Scaffolding Ledger End
It is understood that the beam of this section is located in the subgrade section on the Zhuhai side of Huangmaohai sea crossing.
The construction of the main bridge is progressing rapidly.
It is transported to the site by beam truck, and the erection takes about 2 hours.
At present, Huangmaohai project has entered a new stage of construction.