The construction bidding of Linhe provincial boundary section of Baotou Yinchuan high speed railway is about to enter the construction stage

1962), The owner of the project is Inner Mongolia High Speed Railway Co., Ltd., and the construction funds come from Inner Mongolia Autonomous Region and China Railway Group.

Mileage / range: dk232 + 100-dk281 + 650.

④ Bridge works: about 11.75km (including 3 super major bridges, 7 major bridges and 1 medium bridge).

② Station works: the existing Wuhai station will be changed to a new alkali cabinet station and Wuhai Haibowan station.

② Subgrade works: about 32.31km.

④ There is one beam yard with 242 holes of framed box girder.

(3) Byzq-08, quantity: ① alkali cabinet track laying base: (track laying scope: dk255 + 177.5-dk404 + 599.7).

The funds have been implemented, the construction drawing design documents are complete, and the tenderee is Mongolia Hebei Railway Co., Ltd.

(2) Byzq-07, quantities: ① subgrade works: about 42.66km.

On November 23, the announcement on prequalification of bidding for construction unit price contracting of new Baotou Yinchuan high speed railway from Linhe to provincial boundary and housing construction project (announcement on behalf of bidding) was issued, and the project is about to enter the construction stage of the whole line.

The proportion of capital contribution of the project is 70%.

You have everything you want here ▼ click the applet below to buy it..

Interested potential bidders (hereinafter referred to as the applicant) are invited to apply for prequalification.

Mileage / range: dk372 + 700-dk404 + 599.7.

Loop Box

The newly built line is 420.25 km, with 9 stations.

Bid section division: this bidding is divided into four bid sections, with bid section numbers: byzq-06, byzq-07, byzq-08 and byzq-09.

Mileage / range: dk281 + 650-dk338 + 800.

2.

2.2 scope of bidding scope of bidding: the mileage of Baotou Yinchuan high-speed railway dk232 + 100 to dk404 + 599.7.

③ Bridge works: about 11.67km (including 5 super major bridges and 1 medium bridge).

② Subgrade works: about 7.7km.

Bidding No.: t0sg202103100 1 Bidding conditions the Baotou Huinong section of the new Baotou Yinchuan high-speed railway of the construction project has been approved by the national development and Reform Commission with the reply of the national development and Reform Commission on the feasibility study report of the new Baotou Yinchuan high-speed railway Baotou Huinong section (including Yinchuan BAYANHOT branch line) (FGJ [2019] No.

② Bridge works: about 14.37km (including 5 super major bridges, 9 major bridges and 4 medium bridges).

③ Bridge works: about 17.24km (including 9 super major bridges and 1 Major Bridge).

Project overview and bidding scope 2.1 project overview construction location: Baotou City, Bayannur City, Ordos City and Wuhai City, Inner Mongolia Autonomous Region # construction scale: the Baotou Huinong section of newly-built Baotou Yinchuan high-speed railway is led out from Baotou Station and passes through Bayannur, Ordos and Wuhai City, Inner Mongolia Autonomous Region and Huinong south station, Shizuishan City, Ningxia Hui Autonomous Region.

30): Chapter I relocation of roads, felling and digging roots, river (ditch), sound insulation windows and temporary land in land acquisition and demolition; Chapter II subgrade; Chapter III bridges and culverts; Chapter IV tunnels; Chapter V track; Chapter VI communication, signal, information and disaster monitoring; Chapter VII electric power and electric traction power supply; Chapter VIII housing; Chapter IX other operation and production equipment and buildings; Chapter X Large temporary facilities and transition works; Chapter XI other contents related to construction.

(1) Byzq-06, quantities: ① station works: new Dengkou west station.

(4) Byzq-09, quantities: ① station works: new Wuhai south station.

Mileage / range: dk338 + 800-dk372 + 700.

The bidding project has met the legal bidding conditions, and now it is subject to public bidding.

⑤ One beam yard, 367 holes of framed box girder.

⑤ Tunnel works: 1, 12.095km.

③ Subgrade works: about 23.17km.

④ There is one beam yard with 527 holes in total.

⑥ New alkali cabinet station building (2000m2), production and living house (128m2) and ancillary works.

Schematic diagram of Baotou Yinchuan high speed railway route ▼ source: Railway Construction Engineering Network Editor: Chen long; checked by: Qiao Hong; supervised by: Chang Shangqi ▼ famous and special products, seasonal fresh…

The content of construction bidding corresponds to the budget section table of preparation methods for design budget (budget) of Railway Capital Construction Engineering (gtkf [2017] No.

Planned construction period: 1430 calendar days, planned commencement date: January 31, 2022, and planned completion date: December 31, 2025.

③ There is 1 beam yard, and there are 301 holes in the fabricated box girder.

⑤ New Dengkou West Railway Station building (3000 m2), production and living house (4046 m2) and ancillary works.