Latest construction progress of Xiaotun West Road relocation house: Fengtai Xiaotun West Road shanty town reconstruction relocation

The above opinions are the application opinions, and the final approval of the urban area shall prevail.

The listed plot of Huanghuagang, the central group project, has been partially vacated.

Property right nature: commercial housing property right management plan delivery time: hardbound delivery in 2021.

After verification, the reporter asked about the progress of the central group in Huaxiang.

Progress of the central group in Huaxiang: the compensation and resettlement plan for the withdrawal of the central group in Huaxiang has been submitted to the district major meeting for approval in principle, the phased implementation plan has been approved, and the implementation subject of phase I has been reported to the district government for approval.

All houses and corresponding supporting facilities will be built in Xiaotun West Road shed reconstruction project in the future, which is mainly divided into three groups.

Xinzhuang village, as the homestead to be demolished in the central group, has been included in the overall plan of the central group.

It is developed and constructed in four phases.

The construction area of the project is 492958.25 square meters, including 286231.31 square meters of residential construction area (including 195147.28 square meters of commercial housing construction area, 91084.03 square meters of resettlement housing construction area) and 206726.94 square meters of other construction areas.

The relocation of villagers can be started after the construction of resettlement houses is completed.

The copyright belongs to the original author.

On November 23, our village invited the households involved in the central group to watch the explanation of the house type of the relocation house and strive for everyone’s opinions.

Planned construction time: from May 31, 2018 to November 30, 2021, the construction area of phase III is 206718.64 square meters, including 116368.84 square meters of commercial housing and 90349.8 square meters of other construction areas.

The construction area of phase IV is 135999.86 square meters, including 78778.44 square meters of commercial housing and 57221.42 square meters of other construction areas.

Planned construction time: June 30, 2019 to December 31, 2022.

Reply content: after receiving the questions from the reporter, our unit arranged Fanjia village staff to verify the questions reflected by the citizens on January 12, 2021.

3.

Content and progress of the relocation and retirement plan of Huaxiang central group question content: is Xinzhuang, Huaxiang, Fengtai District, Beijing (north of Tiantan Hospital) in the Huaxiang central group plan? What is the actual progress of the plan? When can it really be implemented? I hope to get a specific and accurate answer, not just a reply.

111 Xiaotun West Road, Lugouqiao township project type: shanty reconstruction and resettlement plan Number of units under construction: 700 planned commencement time: the relocation of Xiaotun West Road has been started in March 2019.

If all the pictures and words in this article involve the copyright of the work, please inform us at the first time.

2.

I hope to get a specific answer on the progress steps and time.

15MM DYWIDAG Tie Bar

Temporary resettlement fee: one bedroom: 5000 yuan / month, two bedroom: 6000 / month, three bedroom: 7000 / month.

The construction area of phase I is 77256.39 square meters, including 45329.84 square meters of resettlement houses and 31926.55 square meters of other buildings.

At present, the district planning department is planning in the district according to the requirements of the Municipal Planning Commission, and it will be reported level by level after there is no objection.

I’m trying my best to promote, follow up and vigorously carry out medium discourse.

According to the situation reflected by the public, the following measures are formulated: 1.

Since the phased implementation plan has been approved and the implementation subject of phase I has been reported to the district government for approval, when will it be implemented? What are the implementation subjects of phase I? thank.

2.

If there is any infringement, please contact to delete it..

1323 suites are distributed in 6 high-rise residential buildings.

Planned construction time: May 31, 2018 to November 30, 2021.

We will delete the source network of the picture in time.

The other two groups will reserve and build affordable housing for Fengtai District, with a construction area of about 200000 square meters.

Reply on the progress of the central group of Huaxiang on January 12 question time: 2021-01-1220:54:05 question content: 1 Is Xinzhuang village, Huaxiang, Beijing (north of Temple of Heaven hospital) in the plan? I hope to get a clear answer.

Welcome to Beijing relocation housing consultation, Haidian, Fengtai, Shijingshan, Chaoyang, Fangshan, Shunyi, Changping, Tongzhou and Daxing shantytowns relocation resettlement housing: share with you the latest construction progress of the shantytowns relocation resettlement housing project in each district! To add the owner exchange group, please add an assistant wechat: 15810662013 house selection scheme consultation, resettlement house auction sale, resettlement house sale, realization of demolition agreement, realization of house selection list, existing house, auction house, agent sale and cash collection can be operated! Community photo and video: community video: two bedroom Video: three bedroom Video: introduction to Fengtai Lugouqiao Xiaotun West Road shanty town reconstruction and relocation resettlement house project name: Fuyue four seasons project location: No.

Reply: phase I of Huaxiang central group involves one listed plot and two relocated housing plots.

Xiaotun West Road shed reconstruction resettlement house is one of the groups, with a total of 6 buildings, with a construction area of about 100000 square meters.

Scope of the project: East to Guihua Yuquan West Road, South to Vanke holiday scenic residential area, West to the current Army yard and Dawayao village, and north to the land for the state-owned Lugouqiao farm in Beijing.

The construction area of phase II is 72983.36 square meters, including 45754.19 square meters of resettlement houses and 27229.17 square meters of other buildings.

It is reported that the relocation resettlement housing community on Xiaotun West Road is not only refined decoration and delivery, so that everyone can move in with their bags, but also equipped with a kindergarten, health service station, nursing home, community leisure place, etc.

Planned construction time: June 30, 2019 to December 31, 2022.