Construction daily report of work area 1 of Lot 1 of Fuzhou Binhai Express

Daily report on construction of work area 1 of Lot 1 of Fuzhou Binhai Expressway on Monday, January 3, 2022, the weather is sunny and the temperature is 10 ~ 20 ℃ Completion of output value (10000 yuan) 1 planned day completion date completion per capita output value weekly planned week completion ratio 50571.237516143% planned month completion ratio annual planned year cumulative annual completion ratio 150016111% 240001610.6% 2 Completion of construction progress the project unit’s design quantity day plan date completion month plan completion month completion ratio accumulative completion of 75 million% 750 high-pressure jet grouting piles (1-33 shafts) for Fuzhou Binhai express line (railway station) 86400000% 985 six zone jet grouting piles 2700000% 27 eight zone mjsm ³ 209000     0_ 0 0% 2090 bored pile root in Zone 8 5200000% 52 bite pile root in Zone 8 550018200% 55 high pressure jet grouting pile (skirt reinforcement) root in zone 6 24600000% 246 uplift in Southern Zone, column pile root 5200000% 52 other matters (1) outward transportation of earthwork.

project construction personnel management personnel and equipment input remarks I Fuzhou Binhai Express___ Day shift of 1 temporary construction team: 7 persons day shift: 2 persons, 1 forklift_ 2 steel support team day shift: 7 people day shift: 1 crawler crane, 1 set, 3 net spraying team day shift: 5 people day shift: 1 person, 2 air compressors, 2 shotcrete machines, 4 earthwork team day shift: 4 people day shift: 1 person, 3 excavators, 1 long boom excavator, 1 telescopic boom excavator, 5 main team day shift: 160 people night shift: 12 people day shift: 2 people, night shift: 2 people, 1 truck crane, 1 truck crane, 6 enclosure team, day shift: 35 people, day shift: 6 people, 3 excavators, 1 truck crane, 3 sets of full casing rotary bite pile equipment.

safety production of the working face of each work point of the project, medium plate finishing of the third section of the transfer hub, medium plate maintenance of the second section of the transfer hub, skirt reinforcement of the eighth area, water stop construction between piles, concrete pouring of the first section of zone 6, earthwork excavation of the second section of zone 6, V According to the construction plan for tomorrow, the project unit plans to complete 7500750 full casing snap piles (axis 1-33) of Fuzhou Binhai expressway, 27027 high-pressure rotary jet grouting piles (skirt) in zone 6, 2460246 bored piles in Zone 8, 52052 snap piles in Zone 8, 55, 0, 55 main structure hub II Maintenance of middle plate in three structural sections; The second concrete support cutting.

Other matters VI.

0 skirt reinforcement of zone 8 (enclosure structure) was completed today, 157 in total, and the remaining 56; 0 inter pile water stops were completed today, 59 in total, and the remaining 59; 750 cubic meters unearthed today_ Area 6 (foundation pit earthwork) unearthed 1000 m3 today, with a total of 24799 m3.

The pouring of the side wall and the roof of the negative first floor of zone 2 are completed.

The site progress transfer hub floor has been completed; The side wall of the second basement is completed; The middle plate of the first and second structural sections is completed, and the middle plate formwork of the third structural section is installed.

cause analysis and measures taken for unfinished plan today VII.

Area 4 unearthed 0 m3 today, with a total of 784 m3.

Mobilization of equipment and materials today (1) material mobilization: no new mobilization materials; (2) Equipment mobilization: no new mobilization equipment; 8、 No memorabilia..

The hub (foundation pit earthwork) today unearthed 0 m3, Kailei 20752 m3 (design 19947), zone 2 (foundation pit earthwork) today unearthed 0 m3, Kailei 12217 m3, the remaining 0 m3 (design 11500), south area (retaining structure) today unearthed 0 m3, and the earthwork was transported out 8524 M3.

(12.25) the earth excavation of the second section of zone 6 is completed, and the fifth steel support is completed; The concrete pouring of the first section of bottom slab is completed.

Shuttering Magnet

IV.

Skirt reinforcement and water stop construction between piles in Zone 8, and concrete curing of the first section of zone 6 in zone 6.

3、 Construction operation management personnel and equipment input No.