Construction organization -86- technical measures for battery production project

The roof slab in the single slope span direction adopts full-length non overlapping profiled steel plate.

The construction adopts the new technology of roof slab high-altitude moving and pressing construction.

Implement on-site coordination meeting and meet every day to solve the coordination and cooperation between civil engineering and installation, so as not to affect the project progress.

More contents: 1 – project overview 2 – wastewater treatment station 3 – bulk gas station 4 – construction objectives 5 – high altitude operation 6 – overall arrangement of project implementation 7 – arrangement of construction team 8 – main construction stage 9 – construction method of divisional and subdivisional works 10 – elevation measurement control 11 – settlement observation 12 – installation of embedded anchor bolts 13 – Determination of bolt position 14 – formwork removal Concrete curing 15 – Super leveling professional construction 16 – floor construction process 17 – cover and protect with film 18 – formwork installation 19 – concrete pouring 20 – concrete surface treatment 21 – steel structure fabrication 22 – detail design 23 – connection node design 24 – steel structure fabrication process 25 – steel structure processing and fabrication process 26 – setting out Allowable deviation of template 27 allowable deviation of steel after correction 28 cutting 29 allowable deviation of sawing 30 allowable deviation of refined bolt hole 32 allowable deviation of bolt hole spacing 33 assembly principle 34 principle of steel plate splicing 35 allowable deviation of welding structure assembly 36 H-section steel assembly 37 welding H-section steel column fabrication 38 welding process flow chart of steel structure 40 welding rod Table 41 – General Provisions for welding flux selection 42 – submerged arc welding 43 – CO2 gas shielded welding 44 – carbon arc gouging 45 – welding sequence 46 – member derusting method and inspection standard 47 – steel member coating method 48 – derusting and repair of coating defects 49 – Parts prohibited from painting 50 – protection and transportation of finished products 51 – steel structure installation 52 – hoisting of steel columns 53 – roof truss installation and construction 54 – high strength bolt installation 55 – profiled roof panel installation 5 6 – positioning of fixed support 57 – Installation precautions 58 – Installation of sandwich color plate wallboard 59 – fire retardant coating of steel structure 60 – binding of beam and plate reinforcement 61 – binding of column reinforcement 62 – column formwork 63 – beam and plate formwork 64 – stair formwork 65 – precautions for construction of wood plywood formwork 66 – concrete engineering 67 – beam Slab concrete 68 – concrete curing 69 – masonry construction 70 – roof waterproof construction 71 – plastering construction 72 – emulsion paint wall construction 73 – ceiling construction 74 – penetration crystallization wear-resistant floor construction 75 – floor tile floor construction 76 – epoxy floor construction 77 – rolling shutter door installation 78 – aluminum alloy window installation 79 – water supply pipe installation 80 – drainage pipe installation 81 – electrical piping and threading in pipe 82 – lightning protection and grounding works 83 – construction schedule Plan 84 – construction progress control flow chart 85 – resource assurance measures 86 – technical measures} approve and implement group regulations.

Thank # warm Meng for pursuing excellence and Zhai Lijuan for sharing the materials.

(2) strictly control the construction quality of each process, ensure one-time acceptance, eliminate rework, and shorten the construction period with the good construction quality of high-quality products in one-time optimization process; (3) adhere to two shifts for key subdivisional works of the project, such as reinforcement, formwork, installation, etc., concrete pouring, three shifts 24 hours a day, non-stop, no rest on holidays, so as to further accelerate the construction progress.

(5) do a good job in the cooperation between civil engineering and installation to avoid rework.

5.2.3 technical measures (1) new technologies are adopted to improve work efficiency and ensure quality.

Therefore, starting today, I will share the construction organization design of solar cell production projects with you.

Solar power stations, solar water heaters, electric vehicles and energy storage power stations are all based on the mass production of batteries, and solar cell production is the demand side of purification projects.

The new construction technology can ensure the waterproof performance of the plant roof and the tightness of the plant clean room, and shorten the construction period.

Welcome to “purify four groups and follow the regulations” (open the link to see the details.) For more purification materials, please refer to “more than 60 purification materials are borrowed for free 20210927”, “30 purification materials are only used for 9.9”, “video, audio and articles, the purification you want is here”, whether it is “like the author” or forwarding, or even opening the advertisements automatically added in the background in and after the text, Can add a “Shandong big steamed bread” to Xiaobian********************** Chat up Xiaobian..

(4) do a good job in the handover and cooperation of the team, coordinate the construction of civil engineering and installation engineering, improve the construction quality and ensure the construction period.

The assembly of track walking high-altitude pressing plate device has applied for the national patent.

Halfen Frimeda

For example, portable XD laser leveler is used to construct structural floor, which can ensure the flatness and elevation of large-area reinforced concrete floor; During the concrete pouring of reinforced concrete structural floor slab and roof slab, track leveling shall be adopted to ensure its flatness, and the leveling layer for floor slab and roof slab finishing shall be cancelled; The single slope span at the plant level is more than 50 meters.